Updated November 9, 2026. Alyssa message held for Chris’s review. This is a decision checklist, not a claim that the supplier order is wrong.
The two large basement Rec Room lake windows sit beneath the Great Room living and dining glass. Alyssa’s November9 08:39 email explains that the lower mullions cannot align with those above because casement widths are limited. The measured divider offset is about 12¼ inches each side; the overall widths almost match. She considers the appearance acceptable. Chris has now accepted the appearance to allow basement casements. Michelle’s acceptance and any future Oriel/upper-window arrangement are not inferred. Review the annotated elevation and paired model views before replying; this is not a proposal to add rec-room windows.
• Resolve the extra duplicate TW107: two known upper units are located; an additional supplied unit has no distinct known location.
• Reconcile the lower-entry side window W007 and Muskoka deck door E102, absent from this order attachment; check their separate supply paths rather than deleting them.
• Confirm the four inferred sill heights in Michelle’s bathroom, boot/powder rooms and basement W006; source floor-plan locations are marked in the current guide.
• Confirm actual operating clear openings, egress, frame sightlines, rough openings and installation details. Alyssa’s mullion explanation does not certify these.
• Main entry, Oriel and Muskoka connection have separate order paths. Keep already answered fold direction and same-floor-level decisions intact.
The November8 discrepancy report is retained as history. The latest R30 model now uses the supplied ordered frames, including upper windows and revised wall openings. The retained roof fits the checked envelope; no roof redesign is established. The new illustrated issue cards show the approximately5-inch band between lower and upper Great Room frames and the four working sill heights. Prior model/order size differences are not repeated as new owner choices. Model placement assumptions are still explicit, not certified installation details.
Chris reviews this explanation and the detailed audit, asks about anything unclear, and explicitly confirms the outgoing scope. Michelle’s final design choices remain separate. The draft’s copy button is disabled during this hold; no approval or acknowledgement has been fabricated.
Open actual annotated plans and current R30 comparison · Open new nook study brief · Read held Alyssa draft