Quote and payment review — November 15, 2026

No new invoice to pay was located. Both owner invoice tabs say no invoices issued; actual historic billing is retained from builder emails. Paid26-1906 ($62,429.62) remains in posted Mendacity payments; do not pay it again.

Fireplace King estimate28855 — November11

Printed subtotal $19,642.53, HST $2,553.53, total $22,196.06. Rumford1000C, Running Bond refractory. Michelle confirmed Rumford1000 but mentioned grey herringbone lining. Obtain exact model/lining before ordering. Valid30days, subject to site/supplier changes. Floor protection excluded; cap allowance/custom cover/powdercoat/tariffs may change total. Builder fee, masonry and full installed comparison are not established. Muskoka Stone quote expected per AlyssaNovember12. ChrisNovember14 leaves supplier choice to Alyssa; that is not quote acceptance.

Closeout and funding

Mendacity forecast $233,439.46 less $213,345.08 posted = $20,094.38, an unreconciled forecast remainder. New CDE projected cost $33,294.33 beforeHST (+$4,620.00); supporting scope not visible. Well still assigned to Mendacity, cottage CDE $2,360.00 remains unidentified. Reconcile allocations/credits, builder-paid Site Errors and road scope before certifying final cash required. No allegation of duplicate septic billing is renewed.

PavNovember9 repeats $34,456.48 balance due for transfer, outside PattyMac. Do not add its included land-transfer tax again. Chris has scheduled virtual document execution for TuesdayNovember17 at10:30AM, for Mendacity-to-Michelle. ChrisNovember16confirms $34,456.48 paid and $39,341.59 complete current cash inonecheckingaccount. Actual closing andpersonalinsurancehandover remain toconfirm; no additional$22,000 counted andno repeatpayment. No new tax liability or HST closing gate inferred.

CategoryRevised budget, before HSTProjected cost, before HSTOverage, before HST
General Scope$3,419.60$6,832.09$3,412.49
Demolition$21,959.60$26,739.37$4,779.77
Septic decommissioning$669.50$1,984.98$1,315.48
General labour$1,500.00$1,996.00$496.00
Site Errors — builder-paid$0.00$1,099.00$1,099.00
SOH fees$0.00$4,648.22$4,648.22
Client Driven Extras$23,891.59$33,294.33$9,402.74

Total variance $25,153.70 before HST, $28,423.67 including HST. This is against the already-revised $205,015.79 including-HST budget, which includes approved change orders. It is distinct from the new $5,555.84 movement. Do not add the approved blasting change order again.

The extras revised budget $23,891.59 is linked to the Drilled Well selection, but $33,294.33 is a whole-category projected/actual total. That does not prove the entire category or its $4,620.00 increment is well drilling. Well transfer to cottage is still unverified. General Scope covers such broad items as fuel/safety/site requirements, but no evidence assigns the new $296.67 to a specific one. Request transaction dates, supplier descriptions, scope and allocation for both new movements. Previously accepted demolition/Site Errors explanations are not reopened. The $1,099.00 Site Errors remains in the raw projection despite builder-paid treatment; closeout needs the agreed credit/accounting treatment.

Recommendation: obtain the itemized changed-cost breakdown and reconciled closeout; do not call this a new blasting bill, assume duplicate septic billing or treat the raw remainder as an invoice. Forecast $233,439.46 less posted payments $213,345.08 equals $20,094.38 unreconciled. No new payment request located.

Separate cottage question: code73 Client Driven Extras has a $2,360.00 commitment/projected amount, actuals zero. It is on the personal Cottage contract, not Mendacity. No supporting description exposed. Already asked in November9 email; latest draft identifies contract/code explicitly rather than presenting it as a newly discovered cost.

Currentcash management schedule: Mendacitychecking $39,341.59, rawprojectreserve $20,094.38, provisionalother-costheadroom $19,247.21. Pav $34,456.48 PAID; priorapprox$22,000notadditional. No personaltopupindicatedonknownprojectfigures; corporateoperating/taxrequirementsandcloseoutcreditsremainunquantified.