Beaumaris — week of November 16, 2026

Correspondence reviewed MondayNovember16; portal read November15, accounting syncNovember14. Chris sent this week’s emailNovember16 at06:36; no duplicate send needed.

Foundation work is visible. The priorities are appliances, remaining selections and Mendacity closeout.

What changed

• Michelle confirmed Rumford1000, black steel, dark brown timbers and kitchen direction. Grey-herringbone lining is an interest, not final; stairs still need her response. Bookshelves are on hold for cost/materials, limewash can wait.

• Fireplace King quote28855 is $22,196.06 including HST, for1000C/RunningBond. Reconcile model/lining and exclusions; compare the forthcoming Muskoka Stone quote. This is not an invoice to pay.

• Well drilling now appears May3–10,2027. November13 photo and November15 camera show formwork; no completed pour inferred. No routine foundation-crew question.

Actions

• Chris: attend confirmed Goemans Mississauga appointment Wednesday November18, around noon, with Michelle; obtain appliance dimensions before November23 millwork coordination. Attend the scheduled virtual document-execution meeting with Pavandeep TuesdayNovember17 at10:30AM for the Mendacity-to-Michelle transfer; coordinate actual closing and insurance handover; Chris confirms $34,456.48 is paid. CurrentMendacitycash is $39,341.59, complete inonecheckingaccount; noadditional$22,000 counted.

• Michelle: send the still-unsent Oriel/fireplace questions toNada, then resolve fireplace lining, explained stair direction and siding in person. Harper’s additional woods-facing casement and the most recent primary washroom layout are confirmed. Confirmed decisions are not reopened. Current preferences and tools are in the Michelle review.

• Alyssa / accounting: explain new Mendacity extras; complete well/pad allocation and credits, road topping to cottage and closeout reconciliation. Coordinate Nada’s next plans, steel engineering, updated window order and Muskoka exterior door placement; do not separately chase sill heights. Draft retains concise, individually answerable points.

• Nada / design: original projecting Oriel constraints and minimum combined Rumford/three-sided-gas enclosure; resolve measured steel/ceiling interfaces. No new images while the measurement-first hold remains.

Money — separate contracts

Including HSTCottageMendacity
Portal projected total$1,679,668.36$233,439.46
Posted payments$202,310.33$213,345.08
Projection less payments, unreconciled$1,477,358.03$20,094.38

Cottage unchanged. Mendacity projection +$5,555.84 versus November9: CDE +$4,620.00 and General Scope +$296.67 before HST, with supporting transaction scope still unverified. Actual costs rose $6,091.67 before HST; cost-to-complete fell $1,175.00 as Site Preparation actuals increased against its unchanged projection. These are different measures. The well remains under Mendacity; builder-paid Site Errors and credits still require reconciliation. No new invoice located; invoice26-1906 is paid and posted. Retainer fully applied; Normerica refund received.

Drafts and watch

Alyssa correspondence now records Chris’s actual sent email, November16 at06:36. Its five questions await replies; no new follow-up draft is needed. Chris added that Nada is waiting on steel engineering. Michelle’s own Nada questions remain unsent. The Exterior Works Brief was separately sharedNovember15 and acknowledged byAlyssa; do not send another invitation.

Source coverage: emails November2–16 and last three sent Alyssa messages (November16weekly,November15ExteriorBrief,November14fireplace); full November10 transcript;274 group texts from November16 backup/extraction08:05, latest November15 19:01. Normerica gdoc remains unresolved. Current measurements/roof/steel/glazing validation is held. Storage about51.9GiB free: reporting fits, reserve/backup coverage remains open.

Insurance watch: WSIB clearance on file expires November19; refreshed certificate requested. The retained CGL certificate names Mendacity rather than both personal cottage owners; corrected evidence remains unlocated. Align coverage with the legal handover.

Detailed overage investigation: the $28,423.67 including-HST total variance is against the already-revised budget; the new $5,555.84 movement is part of it. Category detail and owner-view transaction limits are recorded in docs/MENDACITY_OVERAGE_REVIEW_2026-11-15.md.

Currentcash management schedule: Mendacitychecking $39,341.59, rawprojectreserve $20,094.38, provisionalother-costheadroom $19,247.21. Pav $34,456.48 PAID; priorapprox$22,000notadditional. No personaltopupindicatedonknownprojectfigures; corporateoperating/taxrequirementsandcloseoutcreditsremainunquantified.