Invoice 26-1906 is paid in full: $62,429.62. Builder receipt dated November 2, emailed November 3, and November 9 portal payment summary agree. Balance due is $0.00; no repeat payment recommendation.
• Cottage projection $1,679,668.36; payments $202,310.33; raw remainder $1,477,358.03.
• Mendacity projection $227,883.62; payments $213,345.08; raw remainder $14,538.54.
• Both are separate unreconciled forecasts from the November 9 authenticated pull, not current bank cash or final closeout bills. Authenticated November 9 refresh completed after owner sign-in; accounting syncs are November 9 at 04:21 cottage/04:24 Mendacity. Amounts are unchanged from November 8.
• Cottage extras committed/projected $2,360.00 before HST, actuals blank. No exposed description: do not assume it implements fill pad. Including HST this explains the $2,666.80 increase.
• Mendacity projected cost before HST is $201,666.92 versus $197,004.56 previously; the $4,662.36 increase explains $5,268.47 including HST. Mixed extras actual/projected cost is $28,674.33 versus $25,052.92. Remaining movement is not assigned to a scope without supporting detail.
• Well remains Mendacity CO $26,997.50 including HST despite the November 3 owner direction to cottage. Confirm paired allocation/deposit/credit implementation and fill-pad footing credit; no manual netting of contracts.
• Cottage septic code 3 still has a $7,000.00 commitment within projected $50,774.88, both before HST. Extra unplanned septic rock is not established duplicate billing.
• Historical road estimates are not a formal current standalone allowance. Road topping reportedly deferred through winter; reconcile remaining scope/fees after the November 4 walk without adding the full old estimate on top of posted costs.
Gas tankless water heater request is included in the November 9 unsent Alyssa draft, not price/order authority. Harper window prices dated October 29 are $1,299.64 single/$1,627.68 double before HST; installed total/fees/configuration are not confirmed. Siding is undecided; research ranges are not quotes. Uphill septic at approximately $10,000 is an AI-recorded feasibility discussion, not an approved spend. Michelle's final choices remain pending unless explicit words establish otherwise.
CO-8 continues its expected missing printed quote-subtotal failure; do not manufacture a subtotal from internally calculated lines. The current owner homepage uses dated portal records; the older detailed bridge/ledger remains history. Hypothetical HST exposure is not a booked liability or independent closing gate.