Prepared October 18. Supplier figures below are documented options, not owner approvals or automatic forecast additions. Builder fee/HST and scope must be compared consistently with current allowances.
| Printed component | Before HST |
|---|---|
| Base: rim foam, sloped-ceiling batts/vents, flat-attic R60 | $15,217.20 |
| Fibreglass exterior-wall option | $13,125.00 |
| Roxul exterior-wall option | $21,000.00 |
| BIB exterior-wall option | $19,120.50 |
Calculated base plus one wall option: fibreglass $28,342.20, Roxul $36,217.20, BIB $34,337.70, before HST and any builder fee. These sums are calculations, not printed grand subtotals. Do not enter them as a source-quote subtotal for a CO.
Questions: Alyssa says supplier would not use Roxul, but the written quote offers it; its Roxul heading says R22 while description says R31. Clarify exact wall/ICF/sound scope and whether flat-attic R60 satisfies the required roof zones. Entry-floor R31 still needs its own answer. A further combined drywall/insulation quote is promised. No change to the owner's year-round performance direction or accepted basement insulation/heating is inferred.
Source: PattyMac1111TondernIslandRd.pdf, bid2997127, October6; October15 Insulation Options email. Supplier says measurements may refine price later.
| Printed line | Before HST |
|---|---|
| 11,444 sqft at $3.25, Level 4 | $37,193.00 |
| Window returns | $2,795.47 |
| Door returns/archways | $2,813.50 |
| Subtotal | $42,801.97 |
| HST | $5,564.26 |
| Supplier total | $48,366.23 |
All basement walls were quoted instead of requested perimeter only. Ask for both comparable scopes and separate required thermal-barrier work from optional finish work. Drop ceiling is TBD at $6.75–$8.25/sqft and not included; no area or installed total established. Michelle's October15 reply appreciates full-scope pricing; it is not approval. Source: Revised Carothers Cottage - Muskoka Drywall (1).pdf and October15 email chain.
Original line $104,300.00 plus October16 winter line $2,500.00, printed subtotal $106,800.00, HST $13,884.00, supplier total $120,684.00. Email calls the revision winter additives; line says winter heat, while boilerplate still excludes winter heat/dewatering/tarping. Clarify this conflict. Supplier quote does not include PattyMac's fee; no new CO or approval inferred. Source: Estimate 1093 (2) (3).pdf; Updated Foundation Quote email October16.
| Line | Before HST |
|---|---|
| Sanitation, Call of the Wild63766 | $197.50 |
| BayrocB26154 progress drilling/blasting/excavation | $30,000.00 |
| 3% of $30,197.50 | $905.93 |
| Management installment5/5, cumulative $19,000.00 | $3,800.00 |
| Subtotal | $34,903.43 |
| HST | $4,537.45 |
| Invoice total (paid October 19) | $39,440.88 |
Arithmetic and attached supplier backup tie. Management is outside the 3% base. Paid in full October 19: $39,440.88, confirmed by Chris and a TD successful bill-payment receipt from Mendacity. Recorded outstanding balance is $0.00. The October 18 portal payments snapshot of $111,474.58 predates this payment; PattyMac receipt delivered October20 confirms the payment; portal posting has not been re-read. No holdback deduction is shown, so accounting treatment still needs clarification. Historical contract diary dates remain on record; unpaid-payment reminders are satisfied. Payment does not establish completion or approval of the revised contracts. Confirmation retained privately; no bank balance or account number published.
Sources: INVOICE_26-1847_from_Patty Mac Inc_.pdf; Mendacity Pictures Site Works Invoice 26-1847 Supporting Documents.pdf, including Bayroc October15 progress draw and sanitation invoice63766.
October16 Alyssa reply: demolition remainder reflects higher tipping fees/disposal weights. Time activity entry August13, Derrick West, walking317excavator over pavement with blast mats, $522.67, is builder-paid Site Errors. Chris October16 14:14 accepts the explanation. Keep raw portal visibility distinct from owner liability; do not re-ask why this cost exists or demand its removal as if owner-billed.