Historical reference. Not current project or cash guidance. Current owner site

The Beaumaris Build

The Beaumaris Build

1111 Tondern Island Road · your private project brief · data as of 2026-10-07 correspondence and portal summary; detailed forecast panels retain older allocations, page generated 2026-10-18 · this page reports and recommends — only you approve, sign or pay

Current review: Week of October 19 — refreshed October 18 · Alyssa draft for Chris · Before/after wording and ask-ID mapping

Where we stand

October 7 catch-up: the October 5 weekly email was already sent. Read the current weekly brief for October 6 replies and owner/design actions.

Retainer fully applied; $0.00 remaining. Both October PattyMac payments are now posted. The portal fee allocation is a temporary projection duplication, not evidence of double billing (Alyssa October 6).

Septic installation is moved in the portal; matching contract documents remain due. Demolition now has a $5,401.14 tax-inclusive difference, not the old $23,483.16. Site-error treatment still needs reconciliation.

Ensuite massing and revised elevations arrived October 6. Bay seat/crank coordination and Muskoka-window dimensions remain open; rafter tails need an owner decision. No new Bedroom 1 gate approval recorded.

Money
watch
Retainer confirmation, demolition adjustments and matching reallocation changes remain open. Forecasts below are the recorded pre-reallocation model; they are not a freshly reconciled cash position.
Schedule
watch
Chris confirms CoConstruct schedule updated and satisfactory. Monitor actual progress and winter cash needs nearer foundation installation; no current schedule or estimate chase.
Decisions
watch
Primary-ensuite massing comes first. Nada has no concerns with Michelle’s windows extending to the floor; final configuration/order direction and nook coordination remain open; Chris's four-wall walkthrough and latest styling await review; earlier layout approval is preserved.
Risk
watch
Keep scope and payment records current. Bayroc's insurance has arrived; the remaining owner-directed documentation requests should not be confused with the earlier request for the certificate itself.

Historical forecast model: the figures and detailed narrative below retain earlier allocations and are not current cash guidance. Use the October 18 portal snapshot in the current weekly brief. Revised contract documents have arrived; owner approval and forecast reconciliation remain pending.

Cottage forecast (incl. tax)$1,720,883.21 – $1,724,762.15
Mendacity forecast (incl. tax)$304,305.88
Cottage retainer — fully applied$0.00
Riding on disputes$3,878.94

The site, as the camera sees it

The wired Nest camera over the front yard has recorded a still every ten minutes of daylight since October 6, 2026. The newest frame is below; the camera page holds every day as a short timelapse, the whole build as one film, and highlight cuts by phase once there are phases to cut.

Latest frame from the front-yard camera: the excavation seen from the house
Latest frame refreshed every 30 minutes while the sun is up Blasting and excavation phase · drill rig on the east rock bench

Camera page: daily timelapses and the whole-build film · MuskokaTex dashboard (all project sites, away from the house network, same login)

Forecast means estimated final cost, including approved changes, recorded direct costs and only the options rated probable. The cottage and Mendacity figures are never combined. These are the recorded estimates before the requested contract reallocation; unpriced scope and unresolved adjustments may change them. Portal read September 25: cottage total $1,617,612.40; Mendacity total $287,702.57 includes unresolved adjustments. The older model below is not a reconciliation of that Mendacity portal total; scope overlap must be resolved first. Cottage retainer: $0.00 remaining, fully applied. Invoices 26-1673, 26-1712 and 26-1808 apply $176,991.15 before HST, the full value of invoice 26-1179. Chris confirmed this in his October 5 sent email.

Next action: Chris confirms the September 28 email was sent to Alyssa. Await her response and reconcile the final sent wording when it reaches the archive. Meghan supplies the next layout work.

Reading this page: unlabeled figures are facts from source documents · [F] fact · [I] the assistant's inference · [Q] open question · [ROM] rough market estimate · [advice] opinion. Full legend in the Glossary.

What changed this week

Decisions on your desk

Ranked by dollars-at-stake × urgency. Each card says who decides, by when, what lateness costs, and the next step.

1
Nail down the blasting overage before Bayroc starts
decides: Chris → Alyssa, before Sept 21 · decide by: before mobilisation on Sept 21 · decision and number both settled — what is left is documentary, and it expires when the crew arrives

The decision is made, the crew is booked — Bayroc, Sept 21 to Oct 9 — and the money is agreed. Drilling and blasting runs about $55,000 against roughly $46,000 budgeted, plus $5,000 for the pre-blast survey and vibration monitoring that was never budgeted, $15,000 to excavate the blast rock against a $13,840 Site Prep line, and $10,000 of swinging-mats labour with no budget line at all. Alyssa confirmed in person on Sept 14 that your ~$28,000 total is right. What has not happened is the paperwork.

At stakeAbout $28,000, agreed verbally and undocumented
Why thenA verbal agreement is worth exactly as much as the memory of the two people who had it. Once the crew is on site the work is time-and-materials in motion.
Cost of lateSection 9 requires both signatures on changes over $10,000 before the work proceeds. Blasting starting without a signed change order surrenders that protection on the largest single variance of the project so far — and leaves the figure open to drift.
2
Pick the fireplace units
decides: Michelle · decide by: order by ~mid-October 2026 [I] · expensive to reverse after framing

The wood/gas back-to-back pair for the great room and nook, plus the corner gas stove for Michelle's room ('like a Stuv'). Direction was set July 7; no models chosen.

At stakeAllowance $14,305.67 pre-HST; the real cost of delay is framing and venting
Why thenInstall is scheduled Jan 19, 2027 with a Township fireplace rough-in inspection; venting, clearances and chase framing depend on the exact models, and framing runs Oct–Dec. Lead times were flagged as 'substantial' on Aug 21.
Cost of lateChosen late: reframe/re-vent changes at cost-plus rates, or a winter install delay that ripples into insulation and drywall.
3
Insulation: BIBS, no wall foam, airtightness bought with detailing
decides: DECIDED — now execution · decide by: decided — but the quotes must land before rough-ins (~Nov 2026) · decided — now a tracking job

Decided 2026-09-02. No spray foam in the wall cavities; keep the contracted BIBS assembly and buy airtightness through air-sealing detailing plus a measured blower-door result. Foam only at the rim joists, the loft cantilever and window openings. This building is for year-round use, which strengthens rather than weakens the decision — the money saved on wall foam goes into the air barrier, where a year-round building actually gains comfort.

At stake$26,164.58 allowance ($22,255.73 insulation + $3,908.85 slab insulation); avoids a $16–26k overrun for ~2.6% of the heat load
Why thenThe permit's own heat-loss calculation: glazing 41.3%, air leakage 35.3%, walls only 10.3%.
Cost of lateThe risk now is reversal by circumstance — a February scramble, or a single-source quote, choosing the assembly for you.
4
The nook pop-out and Michelle's window options
decides: Alyssa → then Michelle · decide by: no hard deadline — but before framing frames the openings [I] · cheap now; expensive once framed

The bulk of the window and door order is released and moving; the held groups can now be selected later and installed separately, so the drop-dead-date pressure is gone. What remains is design work: Alyssa needs to come back on a possible "pop-out" window at the nook, and on larger options for the four main windows in Michelle's room.

At stakeWithin the $114,753.56 package vs $118,450 budget; pop-out and enlargement options unpriced [Q]
Why thenRough openings are framed Oct–Dec; a pop-out is a structural change, not a glass change, so it must land before that framing.
Cost of lateAfter framing, a pop-out means re-framing at cost-plus rates.
5
Pick the siding
decides: Chris & Michelle · decide by: before framing details lock strapping/flashing (~Oct–Nov) [I] · cheap until framing details; expensive after

Cape Cod CCS#73447 (on budget) vs NewTech UH58 Belgian Teak (upgrade). The exterior-finish signoff was due Aug 21 and is already behind.

At stakeUpgrade premium ≈ $22,127 all-in (quote difference $19,011.27 pre-HST)
Why thenThe visible material installs in spring, but substrate and flashing decisions ride with framing.
Cost of lateSubstrate rework, or the decision gets made for you by the framing detail.
1.8
Is there a support post at the kitchen island?
decides: Chris → Nada / structural engineer · decide by: before framing (Oct–Dec) · irreversible once framed

Chris's understanding has been that the mid-span steel beam was what allowed the support post at the corner of the kitchen island to be removed. But the timber allowance text says the living-room steel beam "has been replaced with a wood beam", while the July 7 design meeting recorded a "mid-span steel beam with support post at kitchen island corner (confirmed required)". Those cannot both be right.

At stakeA permanent post in the middle of the kitchen — or not
Why thenIt is a structural element. Discovering it after the fact means living with it or paying to remove it.
Cost of lateRe-engineering a beam and its bearing after the floor is framed.
2.2
Timber quotes: get the budget answer before signing anything
decides: Chris → Alyssa · decide by: PineRidge pricing expires ~26 September · cheap now — nothing is signed

Two quotes arrived Sept 3 — PineRidge for solid structural Douglas Fir and Hollow Timber for decorative box beams. They cannot be decided as delivered: there is no total, no budget comparison, and one line bundles two different scopes under a single price.

At stake$47,749 – $64,637 all-in depending on scope; and whether it fits turns on a single coding question worth ~$23,000
Why thenTimbers must be installed BEFORE roof framing, and neither supplier has given a lead time. PineRidge also wants 50% on signing.
Cost of lateRe-quoting at expiry, or missing the pre-roof-framing window and paying to work around it.
2.5
Lock the framing-dependent decisions
decides: Chris & Michelle → Alyssa · decide by: before the relevant walls are framed (Oct–Dec 2026) · cheap now; structural later

Framing runs October–December, and a cluster of decisions become expensive or impossible once it is up: basement electrical routing, the Muskoka Room opening, the nook pop-out and Michelle's window sizes, a service cavity in the exterior walls, basement rough-ins for the optional rooms, ducted returns instead of panned bays, and the air-barrier detail at the tongue-and-groove ceilings.

At stakeIndividually small; collectively the difference between a house you can change later and one you cannot
Why thenEvery one of these is a framing operation. None can be retrofitted at a sane price.
Cost of lateRe-framing finished walls, or permanently losing an option (e.g. future walk-out doors in the basement).
6
Decide the back-property road (blast-rock reuse)
decides: Chris · decide by: site visit, week of Sept 7 — while the rock is coming out of the ground · irreversible either way after blasting

Build the road to the back of the property from foundation blast rock: $25,000 pre-tax ($28,250 with HST). PattyMac's math: ~340 m³ of rock coming out, ~319 m³ needed for the roadbed behind the shed. The alternative is hauling ~31 truckloads away at $200/hr plus disposal — and buying rock back later if you ever build the road.

At stake$28,250 cash (Mendacity side — no deposit shields it)
Why thenThis is a use-it-or-lose-it: once hauled, the material advantage is gone.
Cost of lateDeciding later means paying twice — once to haul away, once to import.
9
Both restated change orders approved
decides: DONE · decide by: DONE 2026-09-05 — both approved and verified in the portal · n/a — approve

Both disputes are resolved in your favour. Foundation was restated on Sept 4 from +$27,830.84 to a CREDIT of $9,181.18 — Alyssa combined the foundation, slab and aggregate lines so the quoted price applies to the whole package, exactly the restatement you asked for. HVAC was restated from $18,463.20 to $11,024.22 — she found the $4,500 credit she had negotiated and missed when building the change order.

At stake$44,451.00 of swing in your favour across the two
Why thenNothing is contested any more, and the arithmetic reproduces on both.
Cost of lateNone, but the §9 backlog should not be allowed to rebuild.
8
Start the appliance package
decides: Chris & Michelle with Meghan · decide by: shortlist by late fall; spec by Jan 11, 2027 · cheap now, expensive after millwork drawings

Allowance $11,168.29 [from the V2 contract text; carried into V3 by unchanged totals — confirm]. 'Signed Off Millwork & Appliance Spec' is due Jan 11, 2027, and range fuel, hood venting, panel-ready fridge dimensions and wall ovens all have rough-in consequences long before then.

At stakeUpgrades here are classic allowance-drift territory: a premium range alone can double the line [I]
Why thenKitchen layout is 'to be determined based on costs, appliance package, and functionality' — the appliances drive the millwork, not vice versa.
Cost of lateLate appliance picks reopen millwork drawings at $160/hr design time plus rework.

The money, split by contract

Two contracts, two wallets: the cottage is yours personally; its retainer is fully applied. site-works bills to Mendacity and is cash from day one. Forecasts include the two probable optionals per your rule.

ContractForecast total (incl. tax)Billed / paid to dateLeft to spendNew cash needed
Cottage (personal)
incl. Muskoka Room doors + design fees
$1,720,883.21 – $1,724,762.15 $253,451.30
recorded builder billings and settled direct costs; not confirmed cash paid
$1,467,431.91 – $1,471,310.85 $1,467,431.91 – $1,471,310.85
Historical forecast model; recorded remaining retainer $0.00. Use current weekly brief for dated portal figures.
Mendacity (site works)
incl. the road + land transfer tax & legal
$304,305.88 $111,474.58 $192,831.30 $192,831.30
no deposit shield
What's inside these numbers. Probable optionals (your rule): the road ($28,250, Mendacity side) and the Muskoka Room doors ($37,244.80 = $32,000 retail × fee × tax — a ceiling, since the quote calls it "heavily discounted" but never states the discounted price [Q]; getting that number is an open ask). Everything else on the Optionals board — including the newly quoted Weatherwall enclosure — stays out until you rate it probable. Costs outside the builder contracts are now included: Ontario Land Transfer Tax $32,475.00 plus Lama Law fees and disbursements $1,981.48 = $34,456.48 on the Mendacity side; and on the cottage side, Spencer Douglas architectural design $30,284.00 (fully billed and paid), the Normerica engagement wind-up $20,856.98 (sunk), and Meghan's interior design carried at the $27,120 midpoint of the $18,080–$36,160 band — that one is hourly and uncapped, so it is an estimate, not a commitment [I]. Cottage retainer. Cottage retainer: $0.00 remaining, fully applied. Invoices 26-1673, 26-1712 and 26-1808 apply $176,991.15 before HST, the full value of invoice 26-1179. Chris confirmed this in his October 5 sent email. Booked supplier costs do not prove that an owner invoice or retainer drawdown has occurred.

The three layers behind those numbers

Three different numbers get called "the cost", and mixing them causes most budget anxiety. Kept separate:

Cash paid requires payment evidence and remains separate for each entity; the cottage retainer reconstruction is not a confirmed cash balance. Committed means the value promised to trades. Forecast means estimated final cost, including recorded probable options and direct costs. The table above distinguishes cottage billings from Mendacity payments; it does not combine them.

Committed trades vs. their budget lines (pre-tax)

TradeCommittedBudget linevs budget
Plumbing$41,102.34$52,324.00−$11,221.66
HVAC$83,780.25$76,537.72$7,242.53
Foundation$104,300.00$120,585.49−$16,285.49
Timberframe Work$22,957.34$57,009.04−$34,051.70
Framing Labour$61,300.00$80,100.00−$18,800.00
All committed$313,439.93
4 of 5 commitments came in under their lines. The one overrun — HVAC — is exactly the change order under dispute. (Code 66 includes structural timber and steel; decorative scope remains separate.) The overall cost budget is $1,446,176.49 pre-tax; committed = 21.7% of it. On contingency: this contract carries no contingency line — variances flow straight to you through allowance true-ups, which is exactly why every change order gets audited before signature. Your real reserves are the disputed $3,878.94 and the deferrable-scope floor below.

The floor: minimum to livable

If money ever tightens, about $162,293.66 pre-tax (≈$183,391.84 with tax) of the cottage budget is cleanly deferrable after move-in: the decks ($31,356.02), the stone veneer ($60,223.44), the decorative timbers ($29,951.70) and the painting ($40,762.50). That puts a minimum-to-livable cottage at ≈$1,302,001.41 pre-tax (≈$1,471,261.59 incl. tax), plus the site-works contract. Three caveats: the well and septic (occupancy-critical) live on the site-works side; an owner-directed rescope can attract the contract's 12.5% extras margin; and occupancy with deferred scope keeps the building permit open until everything is finished.

Cash calendar — what you pay, when

WhenWhatHow much / from where
Before the September 29 callCottage: obtain the running retainer balance and timing of booked-but-unbilled costs (ASK-8, ASK-75). Cottage retainer: $0.00 remaining, fully applied. Invoices 26-1673, 26-1712 and 26-1808 apply $176,991.15 before HST, the full value of invoice 26-1179. Chris confirmed this in his October 5 sent email.[Q]
Before the September 29 callMendacity: payment posting verified September 25 (ASK-83 closed); obtain the demolition adjustment explanation (ASK-82).Separate ledger
Before scope is movedObtain matching contract changes for the road, parking, paths and new septic installation, with the requested 3% fee treatment. Do not treat the requested allocation as executed.ASK-72–74
During foundation planningAlyssa to provide interim winter heat, tarping and dewatering costs and their allowance treatment.ASK-55, ASK-85
Where the money comes from: a dedicated cash reserve already set aside for this project, which exceeds the upper forecast. No mortgage, no line of credit — so no construction-financing trust rules apply, and there is no runway question to manage. The amount is deliberately not shown here. Every invoice arrival also starts clocks: 7 days to object in writing, 10 business days to pay (14 calendar days protects the 5% fee discount, worth up to $8,050), 28 days statutory.

Schedule & the winter race

The plan of record (never revised despite the slip — it's owed to you) vs. where things actually track:

MilestonePlanNow trackingNote
Blasting (20 work days)Aug 19 → Sep 15~Sep 1 → ~Sep 28 [I]start unconfirmed [Q]
Excavation (12 wd)→ Sep 30→ ~Oct 15 [I]
Foundation poured→ Oct 20→ ~Nov 2 [I]cold-weather concrete costs start ~mid-Nov [I]
Basement slab + rough-ins→ Nov 24→ ~Dec 7 [I]
Framing→ Dec 28→ mid-Jan [I]winter framing is normal practice
Envelope closed (windows, roof)→ Feb 24, 2027tracks framingwindow delivery is the lever
Occupancy → completeJun 30 → Jul 23, 2027unconfirmedcontract says Aug 6
The schedule as written cannot be built. It has insulation on Feb 18, 2027, the Township insulation inspection on Feb 19, the windows installed on Feb 19, and the roof on Feb 24 — you cannot insulate a building that is not yet closed in, and no inspector passes insulation before the envelope exists. This is not a small slip; it means the winter sequence has never been properly re-planned. It is the strongest argument yet for the revised schedule you are owed, and it should be raised as a sequencing question rather than a date question. [F, from the contract schedule exhibit]

What if blasting doesn't start this week? The plan's slack is already spent: at ~8 working days behind, the pour lands ~Nov 2 [I], about a week before cold-weather concrete measures start costing money (~mid-Nov [I]). One more idle week eats that cushion entirely and puts the Sept 7 road decision on a moving target, since the rock the road needs comes out of the blast. This is why "did blasting start, and who is the blaster" leads Tuesday's agenda.

Move-in reads as July 2027 (occupancy inspection Jun 30, complete Jul 23; the contract paper says Aug 6). The single biggest lever on that date is winter: the foundation contract excludes winter heat, so a late pour starts costing extra rather than sliding the date — cost absorbs schedule risk until the slack runs out. If you delay ordering something, the ones that actually move move-in are the windows (envelope can't close), the fireplaces (framing waits on venting), and insulation (assembly decision gates drywall). Everything else has float (slack — it can slip without moving move-in).

Can it be sped up? Three levers money can buy: paying for winter-heat measures to hold the pour dates rather than waiting for spring warmth; releasing the held window groups early once the drop-dead date is known; and making the fireplace and insulation decisions this month so nothing downstream ever waits on you. There is no contractual lever to compel pace — the contract has no penalty for builder slippage — so the practical accelerators are all on the decision side.

The two disputes

Foundation: the builder measured a whole-package price against one budget line — measured correctly it's a ≈$9,180 credit, not a +$27,831 charge ($37,011 swing). HVAC: the committed cost basis ($90,171.68) exceeds both the quote ($88,280.25) and the figure circulated to you ($83,780.25) with the $4,500 discount unexplained. Both were challenged in writing Sept 1 with the arithmetic attached; both are billed and committed already, which the contract's before-you-sign rule (§9) forbids — noted formally, not waived. Together with the fee-accounting question: $3,878.94 riding. Ball: PattyMac's. Aging: tracked. Your position: hold signatures until the numbers reproduce.

Optionals board — wants, priced and timed

Sorted by last-responsible-moment, not by size. "Record silent" = never scoped or priced in any project document; the note says what it takes to make it real.

Back-property road (blast-rock) — PROBABLE, in the forecast $28,250 incl. HST
status: rated probable by you (Sep 2); included in every forecast on this page · last responsible moment: week of Sept 7 (site visit) — hard deadline while rock is on site

See Decisions #5. The one optional with a true use-it-or-lose-it clock.

Muskoka Room door (E101) — tri-fold accordion · PROBABLE, in the forecast carried at $28,888.77 all-in (Lepage bi-fold $24,820.66 + fee + tax)
status: deferred on budget (Sep 2); direction now a tri-fold accordion folding into the room toward the lake · last responsible moment: ordered after walls are up — but the framing width (131.75") must be set at framing

The new direction supersedes July's pocketing multi-slide. The August Lepage BI-FOLD quote is the closest existing match to a tri-fold accordion and may simply be the right quote [I] — worth confirming rather than re-quoting. Framing width holds regardless of the final unit.

Basement epoxy floor $16,377.00 (V2 contract option; pre-HST) [confirm carried into V3]
status: priced option in contract text · last responsible moment: any time before flooring decisions; easiest during finishing

The basement is otherwise substantially unfinished in base scope: 1,800 sq ft slab WITH in-floor heat already included — a warm, dry canvas. Full finish-out (walls/ceiling/bath) was never scoped or priced [record silent].

Muskoka Room enclosure — NOW QUOTED (Weatherwall) $16,744.39 + HST = $18,921.16 installed ($19,489 all-in if the 3% builder fee applies [I])
status: quoted Aug 28 via Muskoka Lumber's Windows & Doors division; NOT yet rated probable — say the word and it joins the forecast · last responsible moment: before the Muskoka Room framing details lock (fall 2026)

11 units (4 @ 32½×96, 4 @ 34½×96, 3 @ 34⅝×96) plus 8 mull posts, installation included. This is the panelling-over-screens idea you raised Aug 18, and it fits the year-round intent for the building — it extends the room well beyond three seasons. No lead time or price-validity period appears on the quote sheet [Q], and it is a scope CHANGE against the contract's screen-room allowance rather than a like-for-like swap, so the delta needs establishing. Related and separate: the E101 door (in the forecast) and a possible retaining structure at the same room (unpriced).

Basement guest bathroom unpriced [record silent]
status: on your list Sept 2; excluded from the forecast by your rule · last responsible moment: the ROUGH-IN decision is now — plumbing underground is inspected with the slab (winter 2026/27)

Finishing it can wait years; putting the drain, vent and water rough-ins in the slab cannot. Roughing in now is cheap insurance; retrofitting a basement bathroom into a poured slab is not.

Laundry room unpriced [record silent]
status: on your list Sept 2; excluded from the forecast · last responsible moment: layout and rough-ins before framing/plumbing rough-in (Oct 2026 – Jan 2027)

Location matters more than finish: drain, vent, water, power, and a dryer duct run. Decide where it goes before the walls are framed, then finish it whenever.

Harper's room unpriced [record silent]
status: on your list Sept 2; excluded from the forecast · last responsible moment: framing and rough-ins (Oct–Dec 2026) if it's a new/finished space; finishes can follow

Needs a definition before it can be priced: is this a basement build-out, a re-purpose of a permitted bedroom, or a change to the four-bedroom permit scope? If it changes the permitted room count or adds plumbing, it touches the permit.

Harper's bathroom unpriced [record silent]
status: on your list Sept 2; excluded from the forecast · last responsible moment: same as the basement bathroom — rough-ins before the slab and framing close

Same logic: rough-in now, finish later. Two bathrooms roughed into the basement slab at once is far cheaper than one at a time.

Furnishings throughout unpriced [record silent]
status: on your list Sept 2; excluded from the forecast · last responsible moment: no construction dependency, but long-lead upholstery/casegoods run 12–20 weeks [ROM] — start selections by early 2027 for a summer move-in

Entirely outside the build contract. If Meghan's scope grows to cover furnishing, that is hourly design time plus the goods themselves — worth deciding deliberately rather than by drift.

Standing-seam metal roof (vs budgeted mod-bit) +$42,855 all-in premium (+ snow guards $11,307.69 optional)
status: priced comparison only — mod-bit is the decision of record · last responsible moment: roof installs Feb 2027; realistically decide by late fall

The $68,700.59 quote exists to inform, not to pend. Treat as closed unless you reopen it deliberately.

Siding upgrade (NewTech vs Cape Cod) +$22,127 all-in premium
status: two live samples · last responsible moment: with the siding decision (~Oct–Nov)

This is the one aesthetic upgrade currently in play as a real decision — see Decisions #4 and Tradeoffs.

Exterior/landscape lighting base scope only: 7 sconces @ $400 within the $8,497.50 fixtures line [V2 text]
status: no enhancement scoped [record silent] · last responsible moment: conduit/wiring cheap during electrical rough-in (Jan 2027); fixtures later

If you want landscape lighting, say so before walls and grade close — running conduit now costs little; trenching later costs much.

Landscaping & driveway proper explicitly excluded from the build contract — 'separate proposal' [F]
status: unscoped · last responsible moment: spring 2027, but rough grading opportunities exist during excavation

Chris already asked (Aug 24) for cost-effective grading/rock-reuse opportunities during blasting — keep that thread alive at the Sept 7 visit.

Dock / boat port renovation unscoped [record silent]; valuation docs deduct $75,000 for its condition
status: retained structure, 'extremely poor condition' · last responsible moment: no construction dependency; barge mobilization is the cost lever [I]

If a barge comes for any site work, pricing dock repairs for the same mobilization can save real money — worth one question to PattyMac before site works demobilize.

Bunkie resurfacing unscoped [record silent]
status: bunkie retained; septic usable; water feed capped at demo · last responsible moment: no dependency; note its water is currently capped

One bed one bath — it is your only on-site accommodation until occupancy; a light refresh may earn its keep during construction visits.

Guest house refurbishment unscoped [record silent]
status: retained in Phase 1 · last responsible moment: no dependency

Nothing in the record. If wanted, define scope and we price it as its own small project — do not let it enter this contract as drift.

Golf simulator unscoped [record silent]
status: never mentioned in the record · last responsible moment: if basement finish-out happens, design the space for it then (ceiling height, power, HVAC)

The basement slab + ICF walls + in-floor heat are a good host; the decision that matters now is only: keep a clear-span zone in any future basement layout.

Path/walkway along the feature rock unscoped (wish-list item, Nov 2025)
status: aspirational · last responsible moment: with landscaping, spring 2027; blast-rock could feed it — mention at the Sept 7 visit

Cheap if it rides the roadway equipment mobilization; standalone later, much less so.

Tradeoffs — what a dollar buys where

Every optional is easiest to judge in units of the other things you could do with the same money. All-in figures include the 3% fee and HST where they'd apply. Items marked [ROM] are rough order-of-magnitude market estimates, NOT record figures — they exist to frame the trade, and real quotes replace them.

If you spend it on…All-in costIt equals…
Siding upgrade (NewTech)≈$22,127≈ the basement epoxy floor ($19,061 all-in) + $3k · ≈ the rejected two-zone heating/cooling premium (~$20–30k) · ≈ 78% of the road
Standing-seam roof≈$42,855≈ the ENTIRE painting budget ($40,762.50 pre-tax) · ≈ 1.5 roads · ≈ 2.2 epoxy floors
Back-property road$28,250≈ the drilled well ($26,997.50) · ≈ 1.3 siding upgrades · buys permanent access vs a one-season aesthetic
Basement bedroom + bath finish-out[ROM] $60,000–$110,000 for ~600–900 sq ft done properly≈ 3–5 siding upgrades · ≈ the masonry veneer budget ($60,223 pre-HST) · the largest single optional on the table
Ceiling texture / specialty ceilings[ROM] $5,000–$15,000 depending on rooms≈ a quarter to half a road · small enough to decide late — ceilings don't gate anything until drywall (spring 2027)
Premium appliance package step-up[ROM] +$10,000–$40,000 over the $11,168.29 allowancethe classic allowance-drift line — decide it deliberately with Meghan, not one appliance at a time
Where your two examples land: the NewTech siding is NOT equivalent to a finished basement bedroom — it's roughly a quarter to a third of one. A path around the outside (if it rides the roadway mobilization) is far cheaper than ceiling texture decided in isolation. The general rule this table encodes: exterior upgrades bought during construction are cheap relative to retrofits; interior finish upgrades (basement, ceilings, appliances) are the opposite — they can almost always be done later at similar cost, so they should never compete with schedule-critical money.

Advisor's answers to your direct questions

Spray, batt, or foam insulation — and is foam worth the lost flexibility?

This got its own research document — options, building science, Ontario cost ranges, and a recommendation aimed directly at your flexibility question. Short version ahead of the detail: full spray foam buys air-tightness you have partly already bought below grade with ICF, and it pays for that with permanence — it encapsulates wiring and plumbing, so a future wall move, added bathroom or leak hunt gets materially harder and messier. A hybrid (foam where geometry and air-leakage demand it, batt in straight wall bays) usually wins on value and keeps the walls serviceable. Read the comparison, then put it to Alyssa with a demand for like-for-like quotes on all three assemblies. [advice — the document carries the sourcing]

Mod-bit or standing seam?

Stay with mod-bit unless you decide you're buying looks and 40-year life for ~$42,855 — the record already treats it as decided, the budget carries mod-bit, and the standing-seam quote was obtained purely for comparison (and is dated March, so it would need re-quoting anyway). This one is done; spend the attention elsewhere. [advice]

Pay extra for the stove or refrigerator?

Decide the whole appliance package at once, against the $11,168.29 allowance, with Meghan, before millwork drawings — never one appliance at a time (that's how allowances die). A premium range or panel-ready fridge is a legitimate splurge IF it's chosen now, because venting, gas, and cabinet dimensions are rough-in decisions. The same dollars spent after drywall cost double in rework. [advice]

What needs attention now?

Finish the written demolition-overrun and contract-reallocation requests, reconcile the retainer, and obtain the primary-ensuite model. CO-8 approval stands; its missing supporting quote is a document follow-up. Keep owner decisions separate from inputs owed by PattyMac and Meghan.

Michelle's page

This section is yours. It tracks only what waits on you, what you deliberately held, and how much room the budget still has for the things you care about. (The Muskoka Room doors are now rated probable and carried in the project forecast at their retail ceiling.)

Timber beams — the live decision between you and Chris
quotes in · nothing signed · no deadline until the builder answers some questions

The exposed timbers in the great room, Muskoka Room and exterior are settled and happening — about $47,750 all in. The open question is whether to add decorative beams to the two bedroom ceilings and a decorative pair through the middle of the Muskoka Room. They hold nothing up; they are there for the look. Two beams per room costs about $7,050 on top of the base, or about $8,985 including the Muskoka Room pair; four beams per room costs about $15,570. The supplier recommends two, not four — at four they sit about 3'6" apart, which they say feels crowded. Solid timber in the bedrooms instead of hollow box beams would be about $16,890 on top of base, which is hard to justify for members carrying no load. One thing that takes the pressure off: these beams are surface-mounted after the ceiling is up, so unlike almost everything else here they may be genuinely deferrable to a later year — being confirmed.

Corner stove spec for your room
owed since Jul 7 ('Michelle to send specs') · order by ~mid-Oct [I] · late = reframe/re-vent at cost-plus

Direction on file since Nov 2025: a Stuv 16-78H appears on the schematic, and in June Chris told Wayne at Fireplace King you wanted 'a gas burning unit in her bedroom, like a Stuv'. Wayne asked you to call to go over options — the record shows no call. On July 7 you were also to send the 'Canadian vertical model' you were leaning toward; that unit has never been named in writing. Your bedroom ceiling heights and the 16" sill height are both confirmed, so the corner geometry is answerable now.

Fireplace pair (great room / nook)
models unselected; lead times 'substantial' · order by ~mid-Oct [I] · late = framing waits or reworks

Back-to-back offset pair decided Jul 7 — wood facing the great room, gas facing the nook. Showroom trip is the unlock; it gates framing details in Oct–Dec.

Your four main windows — larger options
no deadline pressure · Alyssa owes you options and pricing

The bulk of the window order is released and the held groups can be selected later and installed separately, so the drop-dead worry is retired. What's live is the upside: Alyssa is following up on larger options for your four main windows (and a possible pop-out at the nook), against the wraparound-view intent you set in March — 'extend the two windows toward the fireplace for more of a wraparound view effect'. Only real constraint: it must land before framing frames the openings.

Pinterest follow-through
session held Sept 1; notes not yet received

The curated-board approach you set up is the backbone of the interior direction. The notes request to Meghan is drafted and ready to send.

Design budget room — is there still money for what you care about?

'Is there still money for the things I care about?' — the honest answer: the interior-finish allowances are almost entirely uncommitted. The rows below are the budget lines your selections draw against (pre-tax, from the builder's own budget page, Sept 1). Nothing you care about has been spent out from under you. One footnote: the windows row shows $0 committed because the Sept 1 release hasn't been booked in the builder's portal yet — the released package is $114,753.56 against a $118,450 window budget (the $141,096.48 row is the full windows-AND-doors category). A picture board for the live aesthetic choices (siding samples, fireplace candidates, the stone) is the next upgrade to this page — sample photos go in the project folder and the assistant adds them.

CategoryBudget lineCommittedStill open
Windows & doors$141,096.48$0.00$141,096.48
Siding & exterior material$46,754.06$0.00$46,754.06
Interior finishing material$53,627.61$0.00$53,627.61
Interior finishing labour$45,220.00$0.00$45,220.00
Painting labour$35,355.00$0.00$35,355.00
Fireplaces$14,305.67$0.00$14,305.67
Tile$11,940.19$0.00$11,940.19
Masonry / stone$60,223.44$0.00$60,223.44
Interior doors$15,555.34$0.00$15,555.34
Millwork / kitchen$63,478.90$0.00$63,478.90
Fixtures$33,001.20$0.00$33,001.20
One structural thing worth knowing: your held items and design directives are protected only when they're in writing — the contract has an entire-agreement clause (§23), which is why the Sept 1 release email named your three held groups explicitly. Anything you decide verbally in a session should show up in notes or an email within days; that's why the meeting-notes request is a standing ask.

Design agenda — for the next Meghan session

  1. Meeting notes — every time. Ask for the AI-generated notes from the Sept 1 Pinterest session, and set the standing expectation that notes go out after every meeting. Nothing decided in a design session should live only in memory.
  2. Fireplaces first. Three units to spec (great-room/nook pair + Michelle's corner stove); they gate framing. Showroom visit is planned for next week — bring the shortlist to the session and leave with models chosen or a firm decision date.
  3. Scope is flexible — bill hourly against what's actually useful. The Harmony package was a starting point, not a fixed deliverable list. Michelle has already done substantial work (the curated Pinterest direction) which should give Meghan a head start — so confirm: adjust deliverables to what we actually need, bill hourly at $160/hr, and don't produce package artifacts we won't use. Revisit what that means for the millwork-drawings gap below.
  4. Trim & baseboards. Michelle asked Alyssa (Aug 21) whether tall baseboards are 'still a thing' against all the glass and metal, and got a builder's answer. It's really a design question — bring it to Meghan as part of the material-concepts work so the trim language is chosen deliberately rather than defaulting to the contract's trim schedule.
  5. Steam shower — proceeding. Raised by Meghan and now going ahead. Needs layout, waterproofing detail, glass spec and a rough-in date pinned to the plumbing rough-in (Jan 2027) — plus confirmation of what it does to the plumbing and tile allowances.
  6. Millwork drawings gap. Millwork sketches and interior elevations sat in the White Glove tier, not Harmony — yet the schedule requires 'Signed Off Millwork & Appliance Spec' by Jan 11, 2027. With hourly billing agreed, settle plainly: who draws the millwork, roughly how many hours, and by what date.
  7. Kitchen = appliances + layout together. Layout is explicitly 'to be determined based on costs, appliance package, and functionality'. Run them as one workstream against the $11,168.29 appliance allowance.
  8. Siding sample decision. Cape Cod vs NewTech (+$22,127 all-in). The exterior signoff is already behind (was due Aug 21).
  9. Masonry extent. Product selected (1" Ashlar Muskoka Grey) but unquoted. The allowance is $60,223.44; the July record shows an all-elevation option at $95,328.67 — extent is the real decision.
  10. In-floor heat, main floor. Wish-list item; needs revised floor layout + engineering + HVAC plan, and the HVAC commitment is already placed — so this is now a formal change decision, not a tweak. Price it once, decide it once.
  11. The basement and the optional rooms. Guest bathroom, laundry room, Harper's room and Harper's bathroom, plus furnishings throughout, are now on the optionals list. None is priced. Even if they stay Phase 2, the rough-ins and layout that make them cheap later have to be decided BEFORE the slab and framing close — that is a design conversation to start now, not next year.

Move-in runway

Chris confirms the updated CoConstruct schedule is satisfactory (September 28). The last captured September 25 schedule showed occupancy July 1–5, 2027 and project complete July 28; retain those as dated evidence, not a fresh date verification.

WhenWhat has to happen
Now → fall 2026Work to the updated schedule accepted by Chris. Track actual progress; revisit unavoidable winter costs for cash planning nearer foundation installation.
Winter 2026–27Envelope closes (windows install Feb 19, roof Feb 24). Watch: window delivery confirmations — the one supply chain that can move your move-in.
Early 2027Utility lead times: hydro service work and Bell internet (cut at demolition) both run long in Muskoka — apply/schedule months ahead, not weeks. [I]
Spring 2027Septic install (May) sits only ~4 weeks before occupancy — it needs the signed maintenance agreement and working pumps/alarms before use. Also resolve the water-source ambiguity: the septic filing says 'LAKE EXISTING' with the well 'PROPOSED' — which source serves the house at occupancy? [Q]
60–90 days outInsurance conversion (construction coverage → homeowner policy). One wording check: the Part 12 declaration says the building is not intended for CONTINUAL winter use, which is true but could read oddly to an underwriter given year-round intent — confirm the policy matches how you will actually use the place. Book movers/barge logistics — island access makes delivery windows real constraints (workboat $100/hr is in the rate card).
Before first winterFreeze protection for a year-round-but-not-continuously-occupied house: low-temperature alarms, remote monitoring, a plumbing layout that can be drained, and heat trace where needed. Nothing in the record addresses this yet, and it is the failure mode that actually destroys cottages. [gap]
OccupancyAll 15 permit inspections passed, no outstanding Building Code orders. Note: occupancy ≠ project complete — deferred permit scope (e.g. decks) keeps the permit open until final inspection.
Moving out?Already done — the old cottage was emptied and demolished in August. Where the contents went is not in the record; if storage is costing money monthly, tell me and it joins the cash calendar. [Q]

Risk watchlist — five, priced, watched

Blasting overrun
Exposureallowance $46,136.79, time-and-materials, 'budgetary' by the contract's own words; §11 gives the contractor price + time for concealed rock conditions
Watchdaily blast logs and the first blasting invoice; whether volumes track the ~340 m³ estimate
Winter concrete
ExposureWeather and blasted-ground conditions will affect required winter measures. Chris considers the supplied estimate sufficient; this is unavoidable cost, not a current proceed/avoid decision.
WatchConditions and updated cost evidence nearer foundation installation
Insurance gap
ExposureWSIB clearance is now in hand and the site-works CGL certificate is correct, but the cottage build has no certificate naming you and Michelle, your own builder's-risk is unplaced (blocked on the ownership transfer), and Bayroc has filed no certificate at all before blasting starts Sept 21 — a site loss today still lands in a coverage argument
Watchthe documents simply arriving, or not, this week
Dispute drag
Exposure$47,632 across the two held COs + the fee-accounting question; also relationship capital
Watchwhether Alyssa's answers this week engage the arithmetic or deflect it
The roof assembly has an October deadline nobody has flagged
Exposurethe permit set draws a VENTED roof throughout (ridge vents, 63 mm baffles, cross-purlins). Whether R-31 plus a 63 mm vent channel actually fits the designed truss depth is a shop-drawing question — and if it doesn't, the fallback is an unvented closed-cell assembly, which is a drawing revision and a code conversation, not a product swap
Watchthe engineered shop drawings, due P.Eng-stamped for the framing inspection (Dec 22)
Under-slab insulation may be paid for twice
Exposure$3,908.85 — the rigid slab insulation (Owens Corning 2" Foamular NGX) sits inside cost code 15, and "Hydronics — Amvic R-10" also sits inside SMHC's HVAC scope, now committed at $90,171.68. This is the same pattern as the slab-insulation transfer already in dispute on the HVAC change order
Watchwhether PattyMac can show which party is actually supplying it
Interior trim may not be in the contract at all
Exposurea full-text search of the signed contract finds NO interior baseboard or interior door casing line — only exterior casing (in the dead Normerica package) and installation trim. The comparator bid priced 'all cottage baseboards, window and door jamb extensions and all cottage casing' at $25,000–$30,000 [ROM]
Watchwhether PattyMac can point to the line in CoConstruct
Retainer exhausted; verify future invoice holdback
ExposureRetainer fully applied. Future invoices require cash; Alyssa October 6 agreed to show holdback. Verify the next invoice.
Watchthe next cottage invoice, its supporting documents and the running retainer balance required by section 5.2

Tuesday call prep

September 29 call: work from the current draft and the written responses.

The askWhat a good answer looks likeFallback if deflected
1. Full written demolition explanation (ASK-82)Cause, date known, notice, final cost, fee and error-code treatment, and whether tree removal is included.Keep this in writing; a short verbal update does not replace the full ASK-82 response.
2. Contract reallocation (ASK-72–74)Matching credit/charge documents, 3% cottage fee treatment, septic split and four remaining Mendacity prices.Do not treat scope as moved until matching documents and fee treatment are agreed.
3. Cottage retainer and booked costs (ASK-8, ASK-75)Documented running balance and cost-code invoice timing; no inference from the invoice-tab message.Separate confirmed dates from estimates, and identify what absorbs each delay.
4. Design inputs and structural quote (ASK-64, ASK-101, ASK-104)Supplier scope reconciliation, ensuite model delivery date and final window coordination; timber price is answered.The invoice-based retainer reconstruction remains unconfirmed pending ASK-8.

The record

Everything above traces to source documents held in the project repository — the signed contract, every change order and its quote, both invoices, the permits, and the builder's own budget page (pulled in an authenticated session). The operational ledger — the full change-order register with its three-check verdicts, the rule-by-rule compliance flags with clause citations, and the deposit ledger — lives on the companion page: the Ledger.

Where this site lives: the canonical copy is served from the home NAS at http://192.168.50.200/beaumaris/ (static files on the \\192.168.50.200\web share); the same pages are reachable away from the house through the MuskokaTex dashboard with its login, and a frozen private mirror exists on claude.ai. It regenerates from the project state in the weekly working session (build_site.py + a one-command deploy) — the "data as of" date at the top is the freshness contract. The camera archive under cam/ is written separately by the GEEKOM every 30 minutes and is excluded from the weekly mirror so a site deploy never touches it.

Current formal flags (2 red) — these are the register's own shorthand; the plain-English versions are the sections above, and the check codes (A/B/C) are in the Glossary:

Dates on the clock

Glossary

Every term used anywhere on this page, in plain English, with why it matters here. If you meet a term on this site that is not in this list, that is a bug — flag it in the weekly session and it gets added.

5% early-payment discount (s5.3)
Contract clause: if EVERY invoice for the whole project is paid within 14 calendar days, the management fee drops 5% - worth up to $8,050. One late payment loses it permanently, which is why the cash calendar tracks payment clocks.
[F] / [I] / [Q] / [ROM] / [advice] labels
The page's honesty labels: [F] fact from a named source document · [I] inference the assistant derived (shown with ~ where approximate) · [Q] open question the record cannot answer yet · [ROM] rough order-of-magnitude market estimate, not a project figure · [advice]/[assessment] the assistant's professional opinion, not record. An unlabeled figure is a fact from the record.
Adjudication
A fast statutory dispute process for construction payments: an independent adjudicator decides in 30 days and payment follows within 15, far quicker and cheaper than court. Under O. Reg. 264/25 s.19(1) payment on an approved, unapproved or merely proposed change order is adjudicable — directly relevant here, where four COs over $10,000 were billed or progressed without your signature, making contemporaneous written records your defence.
AFC (Anticipated Final Cost)
The running best estimate of what the finished project will actually cost — original contract, plus approved and pending change orders, plus accepted unbudgeted scope and forecasts on unpriced allowances. It is the assistant's headline number (chosen over earned-value methods), and CoConstruct's own projection has already moved from $1,634,179.47 to $1,657,835.72 — month-over-month movement in AFC is the most informative number on the page.
Air barrier
The continuous sealed layer in the walls and roof that stops air leaking through the building envelope — distinct from insulation, which slows heat, not air. It gets its own dedicated Township inspection (one of the 15 on permit BP-2026-0678), so it must pass before the envelope is covered up.
Allowance
A placeholder dollar amount written into the contract for work not yet priced; when the real quote arrives, the difference between quote and allowance becomes a change order. Every current change order is an allowance being trued up — e.g. HVAC allowance $76,537.72 vs an implied actual cost of $90,171.68 — and contract §5.6 obliges PattyMac to warn you before any allowance is forecast to run more than 10% over.
ASK-n
The assistant's tracking IDs for questions PattyMac owes answers on (e.g. ASK-4 is the 3%-fee question). Aging is tracked so nothing sits silently.
Batt / spray foam / R-value / rim joist
Insulation vocabulary: batts are pre-cut fibre blankets; spray foam is applied liquid that expands and air-seals; R-value measures insulating power; rim joists are the leaky perimeter band where floors meet walls. The insulation decision (Decisions #2) chooses among these.
Bayroc
The blasting contractor, run by Mike. Chosen over Lamoureux ($116,000 plus tax, and uneasy about damaging the bunkie) at about $60,000. Bayroc owns its own excavators and operators, so PattyMac does not have to supply a machine operator for the three weeks of work. On site Sept 21 to Oct 9.
BCIN
Building Code Identification Number — the Ontario qualification a designer must hold to sign building-permit drawings. Nada Mikhael of Spencer Douglas (BCIN 43743) is your qualified architectural designer of record on permit BP-2026-0678.
Budget vs Revised Budget (CoConstruct CO columns)
In each change order, 'Budget' is the original allowance grossed up for HST only (× 1.13) while 'Revised Budget' is the actual quote grossed up for both the 3% SOH fee and HST (× 1.03 × 1.13), and the Difference is the CO amount. The asymmetry is fair only if the 3% was already inside the original allowances as §5 states — if any allowance was loaded without it, every CO on that line overstates the variance by ~3%, which is the systemic question to settle once in writing.
Builder's risk insurance
Insurance on the building itself while it is under construction — covering fire, theft, storm and similar damage to the unfinished work and materials. It is your obligation under §8.3, is still not placed, and is gated on the Mendacity-to-personal ownership transfer (estimated end of September and drifting) — meaning construction is proceeding with this coverage open; the policy (not just a certificate) should cover full completed value including fee, markup and HST.
Building envelope
The weather-tight outer shell - roof, walls, windows, doors. 'Closing the envelope' (here scheduled Feb 2027) means the building is sealed so interior work can proceed regardless of weather.
CDE margin (12.5%)
A 12.5% "change directive/extra" margin under contract §6 that PattyMac may charge only on owner-initiated changes that alter management scope, schedule or occupancy — explicitly not on routine design finalization or first-time pricing of allowances, and material-only upgrades are exempt. Classifying why each change order happened decides whether this extra 12.5% is chargeable at all, which is why the register records an originator category for every CO.
CGL (Commercial General Liability)
The contractor's liability insurance covering injury or property damage its operations cause to others. Contract §7.3 requires PattyMac to provide a $5M CGL certificate naming you as additional insured before commencement — work began Aug 3, it was promised 'in a matter of days' on Aug 24, and it is still missing as of Sept 1.
CGL (Commercial General Liability)
The builder's third-party liability insurance. It pays when the builder's work injures someone or damages property that is not part of the job - a neighbour's boathouse cracked by blasting, a passer-by hurt on site. Contract s7.3 requires $5,000,000 with you named as an additional insured, which is what lets you claim directly on the builder's policy instead of having to sue the builder first. It is NOT the same as your Builder's Risk policy (s8.3), which covers damage to the building under construction itself - CGL protects against what the work does to others, Builder's Risk protects the thing being built.
Change order (CO)
A written amendment that changes the contract's price or scope, which both sides sign before the changed work proceeds. Five COs exist netting +$47,471.50; contract §9 requires both signatures before proceeding on any change over $10,000, yet Foundation, Framing Labour and HVAC were already billed on invoice 26-1673 (Aug 21) while still awaiting your approval.
Chase framing
The framed hollow shaft that hides a fireplace flue or ducting - it must be sized to the exact fireplace model, which is why fireplace selection gates framing.
Checks A / B / C (register shorthand)
The assistant's three tests on every change order: A - the arithmetic reproduces; B - the cost ties to the actual quote; C - the budget line being compared covers the same scope as the quote. Foundation fails C; HVAC fails B and C. The raw shorthand appears in the formal flags list; the plain-English version is the Disputes section.
CoConstruct ('the portal')
The web portal PattyMac runs budgets, invoices, change orders and schedules through. Every 'portal' figure on this page was read from it in a logged-in session on the date shown.
Committed vs Actuals vs Revised (and Cost-to-Complete)
Portal budget columns: Committed = what's been contractually promised to a trade (a signed PO/subcontract), Actuals = what's been billed/spent so far, Revised = the new expected total for the line, and Cost-to-Complete = what's still to spend. Commitment — not invoicing — is the moment a cost becomes real: HVAC shows Committed $90,171.68 placed before your approval (the §9 pattern), and Plumbing's Committed $41,102.34 effectively locked Gibbins' pricing despite the estimate expiring Aug 31.
Concealed conditions
Unknown physical site conditions discovered during work (buried rock, water, bad soil) that entitle the contractor to a price increase and time extension under §11. This clause is live on your blasting site — any rock surprise arrives as a §11 claim, and the register flags §11 claims for the hardest scrutiny because they are the classic route for cost growth on cost-plus jobs.
Construction trust fund (s.7(1))
Under the Construction Act, money advanced under a construction mortgage for the improvement is trust money — it must be used to pay for the project, not anything else. The record is silent on your funding sources beyond the $200,000 deposit (funding.json explicitly says 'ASK CHRIS — cash, LOC, mortgage? Unknown'), so whether trust treatment applies here is undetermined.
Cost code
The numbered budget category every dollar is filed under (e.g. 05 Foundation, 11 Plumbing, 13 HVAC, 645 SOH Fees), so costs, quotes and change orders can be compared line by line. The live Foundation dispute sits inside Code 5, where the portal still plans to spend the Concrete Floor line ($22,557.00) even though MBG's committed $104,300 already includes pouring the slab — a double-count visible on screen.
Cost-plus contract
A contract where you pay whatever the work actually costs, plus the builder's fee and markup, instead of one fixed price. On this project both contracts are cost-plus — the cottage build is actual costs plus a $161,000 fixed management fee plus 3% markup — so cost overrun risk sits with you, which is why backup, audit rights and change-order discipline matter so much.
E100 / E101
Window-schedule item codes from the supplier's quote - E101 is the big Muskoka Room door (retail $32,000 + tax, heavily discounted, deliberately deferred); E100 is its companion opening, also unresolved.
Entire-agreement clause
A clause (§23 here) saying the written contract is the whole deal — verbal promises and side conversations have no legal force. This is why the Sept 1 verbal window release (everything except Michelle's room, the nook, and the Muskoka Room windows) must be confirmed in writing to exist at all.
Flashing / strapping / substrate
The waterproof metal transitions (flashing), the furring strips siding fastens to (strapping), and the sheathing layer beneath (substrate). These lock at framing time even though visible siding installs in spring - why the siding decision has a fall deadline.
Float / slack
Schedule room - how far a task can slip before it moves the end date. 'Everything else has float' means those items can slip without moving move-in.
Form 1.1
The formal written notice of non-payment an owner files within 14 days of an invoice to dispute part of it — and it must state every reason at once, because reasons not stated are lost. If the disputed HVAC change order appears on a future invoice, this is the instrument that lets you pay the clean part and formally hold the contested ~$7,439.
Form 6
The public notice an owner must publish on a construction trade-news website within 14 days after each contract anniversary to trigger the now-mandatory annual holdback release, with payment due 60–74 days after publication. The cottage contract was fully executed Aug 13, 2026, so your first Form 6 duty lands around Aug 13, 2027 — an owner obligation to diarize, not something PattyMac does for you.
Grandfathering (legal non-conforming rights)
The right to rebuild on a lot that today's zoning would not permit, because a building already lawfully existed there — here capped at 120% of the old cottage's floor area and height near the shoreline. It held: zoning was reviewed and permit BP-2026-0678 issued Aug 20, 2026 even though demolition (Aug 12–14) preceded issuance, and the SRPR is the proof of what existed.
Harmony / White Glove
Spencer Douglas's interior-design service tiers. You bought Harmony ($16k-$32k at $160/hr: mood boards, colour/material concepts, selections). White Glove is the bigger tier that includes millwork drawings - which is why those drawings are currently unowned.
Holdback (Construction Act 10%)
Ontario law requires the owner to hold back 10% of the price of work actually supplied, as a fund protecting subcontractors' lien rights — you must keep it even if the builder invoices 100%. Each of your two contracts carries its own separate 10% holdback pool with its own clocks, but no holdback has yet been shown on any invoice, and whether the fee/markup belong in the holdback base is with counsel.
Holdback release / §5.9
Paying out the retained 10% once lien rights expire — now mandatory annually under the amended Act (via the Form 6 process) as well as at substantial performance, and mirrored in contract §5.9. Because the Act was materially amended effective Jan 1, 2026 (Bill 216, O. Reg. 264/25 replacing 306/18), anything written on pre-2026 rules — including older professional advice — is wrong on holdback and adjudication for this project.
HST gross-up
Multiplying a pre-tax figure by 1.13 to add Ontario's 13% HST. CoConstruct presents everything HST-inclusive (Budget = allowance × 1.13; Revised Budget = cost × 1.03 × 1.13), so comparing a pre-tax trade quote against a portal number without the gross-up is the most common way to get an apples-to-oranges error on this project.
HVAC
Heating, ventilation and air conditioning - the mechanical system. Here: a single-zone system by SMHC including the basement in-floor heating.
Hydronic / in-floor heat
Heating that circulates warm water through tubing embedded in the floor, warming rooms from the slab up instead of blowing air. The basement slab insulation was moved from MBG's foundation scope to SMHC's hydronics scope (Alyssa's Aug 6 email - a $4,746.00 reduction in MBG's quote incl. HST); separately, the original slab-insulation budget line of $4,417.00 incl. HST should come back to you as a credit now that SMHC carries the scope. Two different numbers, both real: one is the quote change, one is the budget line.
ICF (insulated concrete forms)
Hollow foam blocks stacked like Lego and filled with concrete, producing a foundation wall that is structure and insulation in one. Your foundation is ICF by MBG — allowance $82,799.94 against a committed $104,300.00 — driving the +$27,830.84 Foundation CO, which is currently held because its baseline omits the slab and aggregate lines (a possible $37,011.02 overstatement unless credits issue).
Issued for Construction (IFC) drawings
The final, authorized drawing set that trades are allowed to build from — as opposed to conceptual, draft or permit-application sets. Your executed contract's drawing basis is self-contradictory (Notable E cites a Jan 21, 2026 Normerica conceptual file, the Signed Exhibits attach the July 16 draft permit set, and the actual Aug 20 permit-issued set is neither), so establishing which set governs is with counsel; only IFC drawings should authorize work.
Last responsible moment
The latest date a decision can be made without paying for the delay - the sorting key of the Optionals board. Deciding earlier buys nothing; deciding later costs money.
Lien
A charge a contractor, subcontractor or supplier can register against your property to secure money they claim for work on it — preserved within 60 days of the trigger event and perfected within a further 90. Your two contracts run two independent lien clocks, and the 10% holdback plus disciplined payment records are the owner's protection if a sub of PattyMac's goes unpaid.
MBG (Matthews Building Group)
The foundation contractor - footings, ICF walls, slab, waterproofing - committed at $104,300 pre-tax. Their quote is the one the Foundation change-order dispute is about.
Mendacity (Pictures Inc.)
The family company that currently owns the property and holds the site-works/demolition contract. Its invoices are cash from day one (no deposit shields them) and its ledger is kept strictly separate from the personal cottage contract. Ownership transfers to Chris & Michelle personally around the end of September.
Millwork
Custom cabinetry and built-in woodwork - the kitchen, vanities, built-ins. Allowance $63,478.90. Its drawings are the current design-package gap (see Design agenda #2).
Mod-bit vs standing seam
Modified bitumen ("mod-bit") is a torch-applied asphalt membrane for flat/low-slope roofs; standing seam is a premium metal roof of interlocking vertical panels. Mod-bit is what's budgeted and likely ($32,811.91 budget, Advanced Roofing quote $31,880.08); the $68,700.59 standing-seam quote was obtained purely as a price comparison and must never be modelled as a budget overrun.
Open book
A cost-plus arrangement where the contractor shows the underlying evidence for every cost — trade quotes, supplier invoices, employee time records — rather than just a total. §5.1 requires invoice backup including time records, and the CoConstruct 'Open Book' budget view is what let you verify committed figures line-by-line on Sept 1 (surfacing the Foundation double-count and the unbudgeted SOH fee).
Part 12 declaration (OBC energy efficiency)
Part 12 of the Ontario Building Code covers energy efficiency. Michelle signed a Township declaration (Jul 22) that the building is not intended for CONTINUAL winter use. That is truthful and narrow: this cottage is being built for year-round use, just not continuous winter occupancy. It is a permitting formality, not a design brief - the drawings still commit to SB-12 Package A1, so the drawn R-values govern and nobody may use the declaration to insulate below them. Worth one check with your insurer, since the phrase can read differently to an underwriter.
PattyMac / who's who
PattyMac Inc. is your builder. Alyssa Kirk is the project manager and day-to-day contact; Steve MacDonald the president (largely absent since a July car crash); Michelle Battaglia VP Operations (escalation path); Dani Fox accounting.
Preserved / perfected (liens)
The two legal steps that keep a lien alive: registering it on title (preserving, within 60 days) and starting the court action (perfecting, within a further 90). Missing a deadline kills the lien.
Priced option
A quote obtained purely to inform a decision — priced but not accepted, so it is not owed and not part of the budget. The $68,700.59 standing-seam roofing quote is the standing example: the register rules that priced options must never enter the forecast as variances, or the AFC would show a phantom ~$36k overrun.
Prompt payment 7/14/28 clocks
The statutory per-invoice rhythm: object in writing within 7 days or a defective invoice is deemed proper; dispute via Form 1.1 within 14 days stating ALL reasons (one shot); otherwise pay within 28 days — with no exemption for residential work. PattyMac invoices bi-weekly so these clocks restart constantly, and contract §5.2's 10-business-day payment term is actually shorter than the statute allows.
Retainer / deposit
Money paid to the builder up front and then drawn down as a credit against invoices as work is billed. You paid $200,000 on Apr 10, 2026 (before any signed contract); $96,689.26 was applied on invoice 26-1673, leaving ≈$103,310.74 — and §5.2 requires the running balance on every invoice, which has never yet been shown (an $18,939.86 cross-entity misapplication was caught by you on Aug 24 and reissued same day).
Rough-in
Installing the pipes, ducts and wires inside walls and under floors before they are closed up — each rough-in is inspected while still visible, because fixing it later means tearing surfaces open. Underslab rough-ins are scheduled with the concrete floor (Nov 24, 2026), and rough plumbing, rough heating and fireplace rough-in are three of this permit's 15 mandatory inspections.
s.24(1) 90% test
The Construction Act rule that an owner may safely pay out only up to 90% of the value of work actually done — pay beyond that and s.23(1) means you can be forced to pay some of it twice if liens arise. Because $200,000 was wired on Apr 10, 2026 before any contract was signed, cumulative cash-out versus certified work value is a first-class alarm on this project (amber at 88%, red at 90%).
Slab / aggregate / weepers
The concrete basement floor (slab), the crushed stone under and around it (aggregate), and the perforated drainage pipe at the footing (weeping tile / 'weepers'). All three are inside MBG's committed package - which is the heart of the Foundation dispute.
SMHC (Simcoe Muskoka Home Comfort)
The heating/cooling (HVAC) subcontractor, committed at $90,171.68 pre-tax - the figure under dispute in the HVAC change order.
SOH fee (3%)
PattyMac's 3% markup added on top of materials and subcontractor costs (on both contracts). Invoice 26-1673 charged $2,816.19 of it, and the CoConstruct Budget page shows it accruing under Code 645 with a $0.00 budget line — raising the Project Total by $3,182.25 — which is why the open question of whether the 3% was already inside the original allowances (§5 says it was) needs one written confirmation.
SRPR (Surveyor's Real Property Report)
A licensed surveyor's certified drawing of a property showing exactly what buildings stand where, with dimensions and setbacks. The SRPR at permit-package p.46 (Coote Hiley Jemmett, surveyed 2021-11-10) records the now-demolished cottage at 1,068.6 sq ft and 26.5 ft high — it is the sole evidentiary basis of your 120% grandfathering entitlement (new height 28.5 ft = 107.5% of old) and must be preserved permanently.
Substantial performance
The legal milestone when the building is ready for its intended use and the remaining work is worth less than a statutory formula amount (3% of the first $1M of that contract's price + 2% of the next $1M + 1% of the rest) - it starts the major holdback-release and lien clocks. Each contract has its own test: on the cottage contract (total $1,639,197.40) the remaining-work threshold is $42,783.95; on the site-works contract, $6,141.16.
Swinging mats
Blast mats are 6,000 lb rubber-and-cable mats laid over a blast site to stop rock flying. 'Swinging' them means an excavator lifting them onto and off each blast area - real labour, repeated every shot, for the duration of the blasting. This is the $10,000 line with no budget home.
Tarion / HCRA 'contract home'
Ontario's new-home warranty regime: a home built on land you already own is a 'contract home' — the builder must be HCRA-licensed and the home enrolled with Tarion for warranty coverage. Whether this seasonal/recreational cottage is eligible is fact-specific and nothing in the record confirms enrolment or licensing; a Part 12 'seasonal use' energy-efficiency exemption signed 2026-07-22 may interact with warranty, insurance and financing, and the record says to confirm at the start.
Time and materials (T&M)
Pricing where you pay actual hours and materials rather than a fixed price - all risk of overrun sits with you. Blasting is T&M against a $46,136.79 'budgetary' allowance, which is why it leads the risk list.
V2 / V3 (contract versions)
Drafts of the cottage contract: V2 (April 21) and V3 (July 7) preceded the signed July 21 version. A few option prices (basement epoxy, appliance allowance) are verified in the V2 text and carried forward because the totals never changed - marked '[confirm]' until checked against the signed PDF.
WSIB clearance
A certificate proving the contractor's Ontario workplace-injury insurance account is in good standing, so if a worker is hurt the owner cannot be chased for unpaid premiums. §7.3 requires it, it has never been provided; verify it yourself free at clearances.wsib.ca (never accept a contractor-supplied copy), re-pull each payment since clearances expire ~90 days, and note the 'home renovation' exemption does not apply to new builds — no trade on this site qualifies.
WSIB clearance
A certificate from Ontario's Workplace Safety and Insurance Board confirming a contractor's workplace-injury premiums are paid up. Without it, an owner can be held liable for the contractor's unpaid premiums. Received for Patty Mac Inc. on Sept 8 (certificate A0000JYXX5, valid Aug 20 to Nov 19, 2026) - it expires every 90 days, so a fresh one is needed before any payment after mid-November.