Beaumaris — week of October 5

Refreshed Wednesday October 7, 2026. Catch-up brief, not a claim of Monday delivery. Drive sync succeeded today; correspondence through October 6 and both portal summaries checked October 7. Chris's October 5 weekly email is already sent.

The retainer is exhausted, the septic budget has moved to the cottage, and design coordination is progressing; corrected contract paperwork and remaining budget differences still need attention.

What changed

• Cottage retainer: $0.00 remaining. Invoices 26-1673, 26-1712 and 26-1808 apply $96,689.26 + $21,167.71 + $59,134.18 = $176,991.15 before HST, the full original retainer value on invoice 26-1179. Chris confirmed this October 5. Our former $178,832.29 balance was wrong. Alyssa agreed October 6 to show holdback on future invoices.

• Both PattyMac cash payments are posted: cottage $2,310.32; Mendacity $12,596.39. Spencer Douglas invoice 2217 was revised to actual hours and paid at $4,429.60 on October 5; the earlier $7,232.00 demand is superseded.

• Alyssa explains that the 3% fee is budgeted within categories but billed to its own code; projection duplication clears as categories close. This is not evidence of double billing. Source: October 6 reply to the weekly email.

• Ensuite massing and additional dimensions arrived October 6. Michelle approved bedroom windows to the floor and the oriel concept October 2; the October 6 recap still leaves nook and large Muskoka-window dimensions subject to coordination.

Chris — decisions and management

• Rafter tails: review Alyssa's October 6 marked-up timber drawing with Michelle and say whether to retain the Muskoka-room tails. Before fabrication details are finalized; no supplier deadline given. Late changes may require drawing/fabrication revision.

• Review this brief and optional follow-up draft. No repeat weekly email is needed. Normerica refund, Bedroom 1 orientation and removal of the six-inch build-out remain answered.

Michelle — design choices

• Supply vanity/storage references before Meghan develops the ensuite millwork. Layout is still being coordinated; no final ensuite or newer Bedroom 1 styling approval inferred.

Alyssa / PattyMac — owed to us

• Matching septic credit/charge contract documents and corrected Mendacity proposal; road, parking and paths follow once priced. October 6 minutes report septic-field blasting authorized under the cottage code. Bayroc's October 2 quote lists $7,000.00 across three lines; $8,147.30 with assumed 3% builder fee and HST is calculated, not a printed all-in quote. Formal change order remains due; no portal approval entered.

• Demolition reconciliation: current portal excess is $5,401.14 including HST, down from $23,483.16. ASK-82's full item was sent September 28; Alyssa identified an incorrect charge September 29. Explain the remaining difference and reconcile $522.67 before HST still shown as site errors, which Alyssa says PattyMac covers.

• R60 flat-roof comparison, second insulation quote/mineral wool, entry-floor R31 scope, basement ICF drywall, energy-advisor/blower-door and electric floor-heating prices; basement floor alternatives before the pour. Soundproofing exclusion typo answered. Winter T&M accepted; no fresh decision requested now.

• Pre-blast survey and monitoring records; Cape Cod sample tracking; roof coating/granular-seam information. Planned blast timing is not evidence of actual commencement.

Meghan / design — owed

• Clean dimensioned ensuite plan; plumber's shower-swap/steam-generator advice and glass supplier's internal-door feasibility; Toto/washlet examples. Additional dimensions were supplied October 6, so do not re-ask for initial massing.

• Coordinate bay seat, cushion, crank and visible frame with revised elevations before dimensions are locked. Next meeting reported Tuesday at 1:00 in October 6 minutes; verify the calendar invitation.

Money — separate contracts

October 7 portal snapshotCottageMendacity
Portal projected total, including HST$1,677,001.56$213,973.24
Posted payments$202,310.32$111,474.58
Portal total less posted payments$1,474,691.24$102,498.66

These differences are arithmetic, not invoices due or reconciled final amounts left to spend. Fee allocation, matching contract documents and unpriced work remain unresolved. The older detailed bridge uses pre-reallocation assumptions and is not the current cash forecast. No combined contract total is presented.

Draft and verification

Build verification: All builders and image checks passed; only the expected CO-8 B1 validation failure remains. Deployment uses the GEEKOM helper, which authenticates locally and preserves the camera archive. Deployment results are recorded in the work log.

The Alyssa working draft is an optional follow-up, not an unsent copy of October 5. It removes answered questions and focuses on residual accounting and document delivery. Nothing sent, signed, approved or paid by the assistant. CO-8's missing printed quote subtotal remains an expected validator failure; no subtotal invented.

Primary evidence: October 5 sent weekly email; Alyssa's September 29 and October 6 replies; October 6 ensuite meeting-minutes email, rafter-tail email and revised elevations; Bayroc PATTYMACTONDERNSEPTIC.docx dated October 2; invoices 26-1179/1673/1712/1808; October 5 invoice-2217 payment confirmation. Portal figures are recorded in assistant/data/weekly_review_2026-10-07.json.