Beaumaris Ledger

Beaumaris Ledger

1111 Tondern Island Road, Beaumaris · two contracts, two ledgers — never netted · generated 2026-10-18 · draft-for-approval: this page reports; only Chris approves, signs or pays
Cottage AFC — portal
$1,617,612.40
matches CoConstruct projected
AFC if disputes prevail
$1,613,733.46
Foundation restated + HVAC at circulated
Riding on disputes
$3,878.94
Foundation baseline + HVAC basis + fee adj
Reconstructed retainer [Q]
$0.00
Invoice 26-1712, 2026-09-04 · portal unconfirmed · ASK-8
Mendacity AFC
$269,849.40
unsigned proposal · roadway would add ~$0.00
Red flags
2
6 amber · next invoice 2026-10-30

Change-order register

IDChange orderContractAmount (incl. HST)Status · checksApprovals & notes
CO-1Foundation - MBG
5 - Foundation · issued 2026-08-17
cottage−$9,181.18 approved reconcilesPM 2026-08-17 · Chris 2026-09-05
CO-2Framing Labour - MBG
7 - Framing Labour · issued 2026-08-17
cottage−$14,532.93 approved reconcilesPM 2026-08-17 · Chris 2026-09-01
CO-3HVAC - SMHC
13 - HVAC · issued 2026-08-18
cottage$11,024.22 approved reconcilesPM 2026-08-18 · Chris 2026-09-05
CO-4Plumbing - Gibbins
11 - Plumbing · issued 2026-08-27
cottage−$11,287.11 approved reconcilesPM 2026-08-27 · Chris 2026-09-01
CO-5Drilled Well - Gibbins
02 - Site Preparation · issued 2026-08-27
mendacity$26,997.50 approved reconcilesPM 2026-08-27 · Chris 2026-09-01
CO-6Blasting - Bayroc
02 Site Preparation · issued 2026-09-14
mendacity$29,338.43 approved reconcilesPM 2026-09-14 · Chris 2026-09-15
CO-7Excavation of blast rock
02 Site Preparation · issued 2026-09-14
mendacity$1,350.12 approved reconcilesPM 2026-09-14 · Chris 2026-09-15
CO-8Structural Timbers / Structural Steel
66 - Structural Timberframe · issued 2026-09-18
cottage$3,530.99 approved fails checksPM 2026-09-18 · Chris 2026-09-22
Every CO runs three checks before approval: arithmetic (allowance × 1.13 / cost × 1.03 × 1.13) · quote-tie (cost basis = quote subtotal) · baseline coverage (baseline lines span the quoted scope). The third check is what caught the $37,011.02 Foundation baseline error.

Budget bridge — cottage

Base (portal) $1,634,179.47 → AFC as portal states $1,617,612.40 → if disputes prevail $1,613,733.46
Approved change orders (credits net)
−$20,446.01
Pending change orders as issued disputed
$0.00
Pending if disputes prevail if disputes prevail
$0.00
3% fee budget adjustment disputed
$3,878.94
[Q] Portal base $1,634,179.47 vs contract document ≈ $1,639,197.40 — a $5,017.93 gap, unexplained. Priced options (standing-seam roof $68,700.59) are excluded from every figure on this page.

Money at risk — rule firings

Deposit ledger — cottage (personal)

DateEventAmountNote
2026-03-24retainer_invoiced$200,000.00Retainer invoiced as $176,991.15 + HST $23,008.85 = $200,000.00. Credit value against cottage billings is therefore $176,991.15 pre-HST; each 'Apply Retainer' line carries HST so the HST already paid is credited too.
2026-04-10deposit_paid$200,000.00Wired; CoConstruct Payment Summary records it 2026-04-13.
2026-08-21retainer_applied−$96,689.26HVAC $26,398.08 (SMHC 35% deposit) + Foundation $52,150.00 (MBG 50%) + Framing labour $15,325.00 (MBG 25%) + 3% $2,816.19. Balance due $0.01. CORRECTED 2026-10-05: previously recorded as 'not issued'; the reconciliation below proves PattyMac applied it.
2026-09-04retainer_applied−$21,167.71Plumbing $20,551.17 (Gibbins) + 3% $616.54.
2026-10-02retainer_applied−$59,134.18Windows 50% deposit $41,684.30 + timber 50% deposit $17,712.50 + 3% $1,781.90 = $61,178.70; retainer applied $59,134.18; $2,044.52 + HST $265.80 = $2,310.32 due in cash.
Balance$0.00confirm on next invoice per §5.2
Mendacity ledger: no deposit (its §5.2 says "No deposit was paid"). The Aug 21 cross-entity misapplication ($18,939.86) was caught 8/24 and reissued the same day — the R1 rule now watches for recurrence.

Open asks — what PattyMac owes us

IDAskToAsked / viaStatus
ASK-1Foundation CO restated against the lines it covers, or slab + aggregate credit COs issued simultaneously [PARTIAL 2026-09-02: Alyssa has combined the foundation items so the CO presents properly. VERIFY the restated CO reads about -$9,180 before signing.] [CLOSED 2026-09-05: both change orders restated and approved]Alyssa Kirk2026-09-01closed
ASK-2Slab insulation allowance ($4,417) credited; foam board confirmed inside SMHC HVAC figureAlyssa Kirk2026-09-01open
ASK-3HVAC clean accounting + CoConstruct figures updated [CLOSED 2026-09-05: both change orders restated and approved]Alyssa Kirk2026-09-01closed
ASK-4Written answer: how is the 3% SOH fee loaded (allowances / code 645 / both) + align CO math and budgetAlyssa Kirk2026-09-01answered
ASK-5CGL certificate (or the obstacle, stated) [PARTIAL 2026-09-04: CGL received naming Mendacity - correct for site works. Second certificate needed for the cottage build naming Chris & Michelle. WSIB still outstanding.]Alyssa Kirk2026-09-01partial
ASK-6Read-back of window release: holding Michelle's room windows (4), nook windows, Muskoka Room doorAlyssa Kirk2026-09-01open
ASK-7AI meeting summaries for all weekly meetings to date [ANSWERED 2026-09-02: Teams transcribe was off, now ON - all future meetings transcribed and sent. Past minutes do not exist.]Alyssa Kirk2026-09-01answered
ASK-8Retainer reconciled and fully applied: invoices 26-1179, 26-1673, 26-1712 and 26-1808; Chris confirmed October 5. Alyssa agreed October 6 that future invoices will show holdback. Verify next invoice implementation; any cottage insurance requirement stays separate under ASK-41.Alyssa Kirk2026-09-14partially_resolved
ASK-9Notes + recap cadence from design sessionsMeghan DuCheneemail drafted, unsentpartially_resolved
ASK-10The DISCOUNTED price of the E101 Muskoka Room doors ('heavily discounted' vs $32,000 retail - number never stated). Owner has rated the doors probable; the forecast carries the retail ceiling until this lands.Alyssa Kirk / Matt Dewar (Muskoka Lumber)Tuesday call / next emailqueued
ASK-11Normerica refund $56,943.03 received in Scotiabank: Chris confirmed September 28; April 9 EFT email and April 10 voucher now imported.Chris (own records)drafted 2026-09-02 / Tuesday callclosed
ASK-12Site meeting next week to settle blasting DEPTH and EXTENT, with proposed depth and resulting floor/roofline elevations sent in advanceAlyssa Kirk2026-09-08discussed 2026-09-08
ASK-13Like-for-like insulation quotes (spray / batt / hybrid) with effective R-values and the air-barrier detail each impliesAlyssa Kirk2026-09-08discussed 2026-09-08
ASK-14Confirm the rough opening and sill detail suit a TRI-FOLD ACCORDION door folding into the Muskoka Room (direction changed 2026-09-02), and whether the August bi-fold quote is effectively the same unit. Framing width 131.75in. NOTE: Muskoka Room level question is CLOSED - confirmed same level as main building.Alyssa Kirk / Matt Dewardrafted 2026-09-02 / Tuesday callqueued
ASK-15Weatherwall quote: lead time, how long pricing holds, and how it nets against the contract's screen-room allowanceAlyssa Kirk / Matt Dewardrafted 2026-09-02 / Tuesday callqueued
ASK-16Where do interior baseboards and door casings sit in the budget? No such line is visible in the signed contractAlyssa Kirkdrafted 2026-09-02 / Tuesday callqueued
ASK-17Exact section 23 fireplace allowance figure (price column is clipped off the signed PDF; shows only '$14...')Alyssa Kirkdrafted 2026-09-02 / Tuesday callqueued
ASK-18AI meeting notes from the Sept 1 session, and notes after every meeting going forwardMeghan DuChenedrafted 2026-09-02 / Tuesday callpartially_resolved
ASK-19Why was invoice 2068 ($1,620.30 HVAC design) voided, and does that charge return?Spencer Douglasdrafted 2026-09-02 / Tuesday callqueued
ASK-20Registered Energy Advisor: mid-construction air-barrier walkthrough plus a pre-drywall blower-door test, with a committed target numberAlyssa KirkMonday master email (working draft)queued
ASK-21Confirm the vaulted roof stays VENTED as drawn - does R-31 plus a 63mm vent channel fit the truss depth? Settle at October shop-drawing stageAlyssa Kirk / truss engineer / Nada MikhaelMonday master email (working draft)queued
ASK-22CLOSED by owner September 28: CoConstruct schedule updated and Chris is happy with it. Remove this schedule follow-up from the current draft and brief. This does not certify actual site mobilisation or completed work.Alyssa Kirk2026-09-08closed
ASK-23CLOSED by owner September 28: CoConstruct schedule updated and Chris is happy with it. Remove this schedule follow-up from the current draft and brief. This does not certify actual site mobilisation or completed work.Alyssa Kirk2026-09-08closed
ASK-24Basement electrical to run OVER the lake-side window openings (future walk-out doors); can headers be sized now for a future door height?Alyssa KirkMonday master email (working draft)queued
ASK-25Glazing spec in the released window package and the cost of an upgrade - glazing is 41.3% of the design heat load [CLOSED 2026-09-04: windows ordered, no upgrade options were offered; owner satisfied with specified performance]Alyssa KirkMonday master email (working draft)closed
ASK-26Replace panned joist/stud return-air bays with ducted returns - panned cavities defeat the air barrierAlyssa Kirk / ON PointMonday master email (working draft)queued
ASK-27Air-barrier detail at the 1x6 T&G vaulted ceilings - drawn, not describedAlyssa Kirk / Nada MikhaelMonday master email (working draft)queued
ASK-28Price basement rough-in-only scope (guest bath, laundry, Harper's room + bath) separately from finishing - rough-ins go into the slabAlyssa KirkMonday master email (working draft)queued
ASK-29TIMBER/STRUCTURE: the permit set DOES include steel (Steel Schematic, six HSS 5x5 columns, W-shape beams), so the allowance text saying the steel iBeam 'has been replaced with a wood beam' is stale. REAL QUESTION: is there a support post at/near the KITCHEN ISLAND corner in the permitted design? Owner understood the steel removed it; the July 7 design meeting recorded a 'mid-span steel beam with support post at kitchen island corner (confirmed required)'. Confirm against issued drawings BEFORE framing.Alyssa Kirk2026-09-08discussed 2026-09-08
ASK-30TIMBER: break out item 1a ($33,825) into its five component scopes; separate item 2 ($8,750) into timber tails vs box-beam material with a price for eachAlyssa Kirk / PineRidgeMonday master email (working draft)queued
ASK-31TIMBER: price the exclusions - engineering review, site measurement, telehandler, crane/boom truck, bracing lumber - and give the rate beyond the 1 day of install labourAlyssa Kirk / PineRidgeMonday master email (working draft)queued
ASK-32TIMBER: lead times from both suppliers; PineRidge validity expires ~2026-09-26 and asks 50% on signing (~$20,512.50 + fee/HST on the structural portion)Alyssa KirkMonday master email (working draft)queued
ASK-33TIMBER: Hollow Timber quote carries no date, validity, lead time, payment terms, or statement of whether fabrication and installation are includedAlyssa Kirk / Hollow TimberMonday master email (working draft)queued
ASK-34FREEZE PROTECTION: what does the design include - low-temp alarms, remote monitoring, drainable plumbing layout, heat trace? Informational requestAlyssa KirkMonday master email (working draft)queued
ASK-35HRV to be BALANCED AND COMMISSIONED with a written report at completion, not merely installedAlyssa Kirk / SMHCMonday master email (working draft)queued
ASK-36Is there slab EDGE (perimeter) insulation at the heated slab, distinct from under-slab?Alyssa KirkMonday master email (working draft)queued
ASK-37TIMBER: allowance says eastern white pine but PineRidge quotes Douglas Fir. NOTE the permit column schedule specifies Douglas Fir 8x8 for timber columns, so DF is likely an engineering requirement, not an upgrade. Narrower question: is EWP acceptable for purely DECORATIVE timbers, and is the quote above allowance because of material or because the allowance was low?Alyssa KirkMonday master emailqueued
ASK-38TIMBER: bedroom wing timbers and exterior tails are inside the contracted allowance - if dropped, confirm it comes back as a CREDITAlyssa KirkMonday master emailqueued
ASK-39CLOSED — portal HVAC commitment corrected to $83,780.25 on September 25 reading, matching CO-3 cost basis. Separate scope and competitive-quote inquiries remain.Alyssa Kirk2026-09-08answered
ASK-40Cottage invoices to show the 10% statutory holdback as its own line, with a running balance (owner will apply holdback on the cottage contract)Alyssa Kirk2026-09-08discussed 2026-09-08
ASK-41Second CGL certificate for the COTTAGE build naming Chris Carothers and Michelle Lovretta Carothers as additional insureds, timed with the ownership transferAlyssa Kirk2026-09-08discussed 2026-09-08
ASK-42Stop labelling approved change-order scope (e.g. the drilled well) as 'Client Driven Extras' on invoices - s6 attaches a 12.5% margin to that category and the label should not become a precedent. Only 3% was charged, which is correct.Alyssa KirkMonday master emailqueued
ASK-43CLOSED: Bayroc certificate of insurance received 2026-09-18. Two quotes on file. Pre-blast survey, ground vibration monitoring and blast design are line items in the Bayroc quote at $5,000.Alyssa Kirk2026-09-11answered
ASK-44Site visit date for blasting depth/extent AND road options - owner available any day this week [CLOSED: site walk held 2026-09-10]Alyssa Kirkmeeting-notes email 2026-09-08closed
ASK-45NOOK POP-OUT: pricing only. The lot-coverage assessment has cleared - the added area was assessed as acceptable, so permitting is not a gate. Needed: cladding (by material), installation, masonry, and whether Matt Dewar has a one-piece system. Glass is known at $3,697.08.Alyssa Kirk / Nada Mikhaelmeeting-notes email 2026-09-08queued
ASK-46Michelle's main bedroom windows: pricing and options to extend higher and lowerAlyssa Kirkmeeting-notes email 2026-09-08queued
ASK-47Great Room fireplace choice remains open pending current visualizations. Owner hopes early week. Do not order; supplier framing/venting/lead-time cutoff needed. Supersedes old instruction to place order.Alyssa Kirkmeeting-notes email 2026-09-08on_hold_owner_selection
ASK-48Start the appliance package: budget and spec, so Meghan can design the kitchen around real dimensionsAlyssa Kirk / Meghan DuChenemeeting-notes email 2026-09-08queued
ASK-49CLOSED: MEETING NOTES NOW BEING PRODUCED. Alyssa sent "Meeting Notes - September 22nd" on 2026-09-22 - seven topic summaries plus twelve assigned follow-up tasks with owners. An AI transcript test was run 2026-09-21. The standing expectation is met; what to watch is that it continues and that Meghan's sessions get the same.Alyssa Kirk2026-09-21answered
ASK-50Revised number for the road and fill scope as walked 2026-09-10 - now includes parking behind the guest house and walking paths around both sides to the lower-level side door, beyond the original $25,000 roadway quoteAlyssa Kirk2026-09-11outstanding
ASK-51WITHDRAWN 2026-09-14 (owner): septic tank placement is nowhere near the blasting area, so the permit-layout and well-clearance concern does not arise. No action.Alyssa Kirk / Aidengo-ahead email 2026-09-11withdrawn
ASK-52Generator relocation and larger propane tank: pricing, timing, and recommended tank size given the gas fireplaces and heating loadAlyssa Kirk2026-09-11outstanding
ASK-53CLOSED: Answered 2026-09-14: the septic field blasting is NOT in the Bayroc quote. Superseded by ASK-61 (get it priced).Alyssa Kirk2026-09-14answered
ASK-54CLOSED 2026-09-14: Alyssa confirmed IN PERSON that the owner's blasting arithmetic is correct - roughly $1,000 excavating, $9,000 blasting, $10,000 swinging mats, $5,000 survey and monitoring, plus HST, about $28,000 total overage. Verbal confirmation only; the written change order is still outstanding (see ASK-59).Alyssa Kirk2026-09-09answered
ASK-55Estimate received and sufficient per Chris September 28. Remove winter-cost item from weekly email. Required measures will proceed; weather and blasted-ground conditions determine cost. Revisit cash forecast closer to actual foundation installation, not as a current proceed/avoid decision.Alyssa Kirk2026-09-21closed_sufficient
ASK-56TIMBER PHASING. PARTIAL ANSWER surfaced in the 2026-09-15 transcript: Alyssa confirmed verbally that all decorative timbers and box beams can go up at any point - 'a month after you move in. You could do them in 10 years' - with no roof, framing or drywall gate, provided there is good blocking to fix into. Timber spec stated: Douglas Fir, No. 1 grade, D45, unfinished, connections, delivery and shop drawings included, eased edges as priced. STILL UNANSWERED: the same confirmation IN WRITING (the s23 entire-agreement clause means a verbal confirmation is not protected), the specific blocking schedule to be built into framing in January 2027, and the cost of a second mobilisation.Alyssa Kirk2026-09-21partial
ASK-57CLOSED: Answered 2026-09-14: the MW Stoneworks quote covers all masonry for the project, interior and exterior, from the estimator's takeoffs. Alyssa is having MW restate it with quantities - tracked as ASK-62.Alyssa Kirk2026-09-14answered
ASK-58CLOSED 2026-09-21: Meghan's presentation moves OFF the Tuesday call to Thursday 2026-09-24 from 10:00 - she asked for one or two extra days. Agreed verbally on the 2026-09-15 call. Bay window and bedroom windows remain live under ASK-79 and ASK-46.Alyssa Kirk2026-09-14answered
ASK-59CLOSED: Blasting change order CO-6 ($29,338.43) and excavation CO-7 ($1,350.12) issued 2026-09-14 and approved by the owner 2026-09-15. Bayroc certificate of insurance received 2026-09-18. The 3% fee IS applied on top of the overage - final figure $30,688.55, not ~$28,000.Alyssa Kirk2026-09-14answered
ASK-60CLOSED by owner September 28: CoConstruct schedule updated and Chris is happy with it. Remove this schedule follow-up from the current draft and brief. This does not certify actual site mobilisation or completed work.Alyssa Kirkqueuedclosed
ASK-61Septic blast quote received October 6: Bayroc October 2 document lists $3,000.00 blasting, $2,000.00 mats, $2,000.00 excavation, plus HST. Computed total with builder 3% and HST is $8,147.30, not a printed quote total. October 6 minutes report authorization and cottage allocation; CO still due.Alyssa Kirk2026-09-21answered
ASK-62CLOSED: Scope answered 2026-09-22: MW has included all three sides of the floor-to-ceiling fireplace. The QUANTITY TAKEOFF is still not provided - the reissued file is the same Estimate 1123. Reopened as ASK-96.Alyssa Kirkqueuedanswered
ASK-63Installed fireplace ballparks delivered September 30 (Rumford 1500 $25,000.00; Astra 32 about $12,000.00, before HST). Selection-specific final price, lead time and framing/venting specifications remain due; do not request the initial prices again.Alyssa Kirk2026-09-21partially_resolved
ASK-64CO-8: original price question answered by Pineridge statement ($33,825.00 timber + $1,600.00 stain) and steel quote ($22,957.34), totaling $58,382.34 by arithmetic. Narrow remaining verification to supplier scope/drawing revision and included installation, engineering/shop drawings, connectors and delivery; reconcile old EWP/wood-beam portal allowance with Alyssa’s confirmed Douglas fir and the approved steel scope. These are unclear inclusions, not proven missing work. Do not ask for the price again. Decorative deferral/blocking is separate; ASK-76 is the $1,500.00 commitment gap.Alyssa Kirk2026-09-21partially_resolved_post_approval
ASK-65CLOSED: Superseded proposals voided 2026-09-22 - "Voided - Carothers Cottage 2026 - July 7th" and "July 16th". Alyssa is preserving accounting records before deleting the rest.Alyssa Kirk2026-09-21answered
ASK-66TIMBER FINISH: eased vs chamfered timber edges (eased is what is priced; chamfered is a 1in 45-degree cut, more decorative), and a Sansin stain colour - interior stains for interior timbers, exterior for exterior. Alyssa says not immediately required.Michelle / Chris (decision)internalqueued
ASK-67CLOSED by owner September 28: CoConstruct schedule updated and Chris is happy with it. Remove this schedule follow-up from the current draft and brief. This does not certify actual site mobilisation or completed work.Alyssa Kirkqueuedclosed
ASK-68CLOSED by owner September 28: CoConstruct schedule updated and Chris is happy with it. Remove this schedule follow-up from the current draft and brief. This does not certify actual site mobilisation or completed work.Alyssa Kirk2026-09-21closed
ASK-69CLOSED by owner September 28: CoConstruct schedule updated and Chris is happy with it. Remove this schedule follow-up from the current draft and brief. This does not certify actual site mobilisation or completed work.Alyssa Kirk2026-09-21closed
ASK-70WITHDRAWN 2026-09-21 by owner direction: no pre-meeting email to Meghan. Setting and presenting the agenda is her process to drive. The meeting-notes expectation and the appliance-scope question are raised AT the meeting instead, not imposed beforehand.Chris (internal) - NOT to be sentqueuedwithdrawn
ASK-71Confirm the amount payable on registration of the Mendacity -> Carothers transfer - land transfer tax and legal fees - and whether any related-party or rollover treatment reduces it. Working figure is $34,456.48 from file 26-1147, unpaid. Also confirm what, if anything, has to be in place before the forms can be executed.Lama Lawqueuedqueued
ASK-72Septic installation moved in portal budget: matching credit/charge contract documents remain due (Chris October 5, Alyssa October 6). Road, parking and paths follow once priced. October 6 minutes now assign septic-field blasting to cottage, superseding the September allocation request; decommissioning remains Mendacity.Alyssa KirkDraft for week of 2026-09-28; Chris sendspartially_resolved
ASK-73Alyssa September 29 accepted reallocation without extra fees. Verify matching contract documents carry agreed fee treatment; do not repeat the original hypothetical margin charge as an incurred cost.Alyssa KirkDraft for week of 2026-09-28; Chris sendspartially_resolved
ASK-74Septic blasting priced separately and reported allocated to cottage October 6. Mendacity decommissioning now projects $1,984.98 against $669.50 pre-HST; generator/propane pricing remains to reconcile. Earlier four-item $30,000 swing is historical, not the current forecast. Read October 7 portal snapshot.Alyssa KirkDraft for week of 2026-09-28; Chris sendspartially_resolved
ASK-75Retainer timing resolved: exhausted by invoice 26-1808; Chris confirmed paid October 5 and portal now posts $2,310.32 on October 6. Earlier $178,832.29 reconstruction was wrong and is superseded. Future cash planning remains separate from this closed balance question.Alyssa Kirkqueuedanswered
ASK-76Code 66 Timberframe shows committed $59,882.34 against a change-order cost basis of $58,382.34 - a $1,500.00 difference. What is the extra $1,500?Alyssa Kirkqueuedqueued
ASK-77Confirm the tax treatment of the Mendacity -> Michelle transfer and the $1.8M shareholder mortgage: the corporate gain on the sale, whether the 4% interest is taxable income to Mendacity and deductible to Michelle, and whether the structure is defensible as at fair market value. Lama Law recommended this on 2026-07-14 and there is no record of it having been done.Accountantqueuedqueued
ASK-78TITLE NAMING: the mortgage instruction of 2026-06-24 records cottage ownership as MICHELLE LOVRETTA alone, not jointly with Chris. The insurance workstream has been asking PattyMac for a CGL certificate naming BOTH owners, and the cottage build contract is signed by both. Confirm which is intended before the transfer is executed - it changes the insurance certificates, the Builder's Risk policy and the lien position.Chris (internal)internalqueued
ASK-79BAY WINDOW: firm numbers for the outstanding components - cladding, installation, masonry - on top of the $3,697.08 glass. The window itself is approved in principle subject to those numbers; Michelle holds the final call.Alyssa Kirk2026-09-21outstanding
ASK-80CLOSED by owner September 28: CoConstruct schedule updated and Chris is happy with it. Remove this schedule follow-up from the current draft and brief. This does not certify actual site mobilisation or completed work.Alyssa Kirk2026-09-22closed
ASK-81BAYROC INSURANCE - DOWNGRADED 2026-09-22 by owner direction, and the assistant agrees on the analysis. Additional-insured status on Bayroc's policy is not what protects the owners against blasting damage: as third parties they can claim against Bayroc's liability cover without being insureds on it, and that cover is real ($5,000,000, Markel CAS740221, operations described as 1111 Tondern Island Road). Being named would add defence cover if the owners were themselves sued, protection from subrogation, and notice of cancellation - worth having, not worth a fight. DO NOT push PattyMac on this. What DOES matter and stays escalated: (a) COPIES of the pre-blast surveys - note these are ALREADY PRICED inside the Bayroc bid (pre-blast survey / ground vibration monitoring / blast design, $5,000), so this is confirming delivery of something bought, not asking for new scope; (b) Bayroc's WSIB clearance, which the Bayroc quote of 2026-09-09 undertook to supply and which carries direct owner liability under the WSIA; and (c) ASK-41, PattyMac's OWN CGL, which still names Mendacity Pictures Inc. alone and does not describe the cottage build at all. (c) is the material one.Alyssa Kirk2026-09-22downgraded
ASK-82CLOSED: Alyssa October16 explains residual demolition by tipping fees/disposal weights;522.67 Site Errors paid by PattyMac, excavator walked over mats due parked golf-course cars. Chris14:14 accepts explanation. No repeat dispute or removal demand. Monitor owner-cost projection exclusion without treating raw portal Site Errors as owner liability.Alyssa Kirk2026-09-22closed
ASK-83CLOSED — September 21 payment $41,001.01 is now posted; portal read September 25. Retainer remains separately open under ASK-8.Alyssa Kirk / Dani Fox (accounting)2026-09-22answered
ASK-84s23 CONFIRMATION PROTOCOL. Now that meeting transcripts and recaps are being produced, propose in writing that the standing practice is: PattyMac issues the transcript and recap after each meeting; the owner replies with a short confirmation of the decisions and commitments taken from it; and PattyMac replies agreeing or correcting. That reply is what s23 actually requires - 'a further written agreement between the Contractor and the Owner' - and a transcript on its own is not. Also ask that where a decision varies scope or price it continues to be papered as a change order, and note that Alyssa's confirmation is taken as binding on PattyMac unless PattyMac says otherwise (the contract was signed by Steve MacDonald as President).Alyssa Kirk2026-09-22to_send
ASK-96MASONRY: the quantity takeoff and the areas the quote covers. The file resent 2026-09-22 is the same Estimate 1123 with no quantities. Scope question answered - all three sides of the floor-to-ceiling fireplace are included. Note the estimate excludes tarp and heat if the work runs in winter; masonry is scheduled 2027-04-23, so that should not bite.Alyssa Kirk2026-09-22outstanding
ASK-97CLOSED: bay-window depth explanation answered at the September 24 design meeting: 20 inches outside the wall plus six inches of wall gives approximately 26 inches. Final shop dimensions and adjacent-window operation remain under ASK-104; all-in cost remains ASK-79.Alyssa Kirk2026-09-22answered
ASK-98BOX BEAMS: separate quote for the bedroom box beams INCLUDING installation. Hollow Beam Co. has provided drawings and two bedroom options; the pricing has not reached us.Alyssa Kirk2026-09-22outstanding
ASK-99SIDING: Alyssa confirms Cape Cod can custom-match a supplied stain sample and will arrange standard colour samples. Mailing address already supplied. Await dispatch/arrival, final colour/width/product details and any custom-stain cost; no selection approved.Alyssa Kirk2026-09-22partially_resolved
ASK-100FIREPLACES: pricing plus options for realistic log or alternative media, smaller efficient gas units for the bedroom, installation timing, venting requirements, and whether OWNER-SUPPLIED appliances can be installed.Alyssa Kirk2026-09-22outstanding
ASK-85Monitor winter foundation costs closer to installation for cash planning, as weather and blasted-ground conditions become known. No current email/call chase; required measures are unavoidable per Chris September 28.Alyssa Kirk2026-09-22deferred
ASK-86SPECULATIVE BLOCKING (owner direction 2026-09-23 - likely the best option): install framing blocking for EVERY ceiling option we might want in the bedrooms, hallway and bathroom - box beams, dropped ceilings, ceiling fans, headboard treatments, bookshelves - so the decision can genuinely be made after the spaces are framed and evaluated. Blocking goes in DURING framing (starts 2027-01-05); a decision deferred past it is not deferred, it is foreclosed. Ask for the cost of blocking everything speculatively, and put it on the agenda for the next meeting.Alyssa Kirkqueued for the week of 2026-09-28 message and the next builder meetingqueued
ASK-87SOURCE LIST: the suppliers Meghan likes to source from for flooring, sinks, fixtures and finishes. Trade-only suppliers are hard to find online, and this is the single highest-leverage ask - it speeds up every subsequent round for both owners.Meghan DuChenedesign meeting 2026-09-24partially_resolved
ASK-88Primary-ensuite massing and entrance views, plus Bedroom 1 design visuals (Chris; Meghan's #2). No model delivered yet. Bedroom 1 images require approved Gate 3D.Meghan DuChenedesign meeting 2026-09-24partially_resolved
ASK-89BEDROOM NUMBERING: renumber the package so it matches the plans - Michelle's room is Bedroom 2. The Stuv fireplace currently appears in Bedroom 1, which is Chris's room. Simple change that prevents a gas line, venting and corner framing landing in the wrong room.Meghan DuChenedesign meeting 2026-09-24partially_resolved
ASK-90CEILING HEIGHTS room by room, and the fan drop that follows. The bedroom ceiling detail and the fans are both being designed against an unknown dimension.Meghan DuChenedesign meeting 2026-09-24outstanding
ASK-91FIREPLACE STONE: swap the proposed stone image - the masonry is already selected (MW Stoneworks, Muskoka Rock veneer). The colour in her image reads well; the stone shape and the pink in it do not.Meghan DuChenedesign meeting 2026-09-24partially_resolved
ASK-92LATERAL FLOOR TRANSITION at the kitchen-to-great-room line, where there is no wall to hide the joint. The owners could not resolve it and want a designer's answer. Ties to the wider zone question - a stone 'L' through entry and mudroom, then wood beyond, or a split by roofline.Meghan DuChenedesign meeting 2026-09-24partially_resolved
ASK-93PINTEREST - pin into the thin sections. The Tondern Rebuild board has 943 pins across 17 sections, and Meghan's package tracks its density: Fireplace (121), wall partitions (116), Windows & Doors (108) and Nook (94) are where the design landed closest, while Bedrooms (11), Bathroom (22) and Stair (13) are the three thinnest AND the three that got pushed back on. Before the next round, add to the thin sections.Michelle (internal)internalqueued
ASK-94PINTEREST - the 'Don't Like / Discuss' section exists and has ZERO pins. The sharpest note from the 2026-09-22 review was negative (the beige-parody observation) and Meghan has no way to see it. Ten pins there would do more to prevent another samey-samey package than a hundred more aspirational ones.Michelle (internal)internalqueued
ASK-95PINTEREST - split sections to match Meghan's page structure. Bathroom (22) currently collapses primary ensuite, powder room and basement bathroom; Bedrooms (11) collapses two different rooms with different occupants and different fireplaces. Add Interior Trim & Doors. The powder room - the one place the palette is meant to break - has no dedicated input at all.Michelle (internal)internalqueued
ASK-101PRIMARY ENSUITE: provide massing with an entrance view, test tub access, vanity size/position, steam/shower door arrangement and enclosed shower. Layout before finishes; no final vanity or wall revision approved.Meghan DuChene2026-09-24outstanding
ASK-102Jason Ng at Goemans Vaughan contact delivered in Alyssa September 29 reply. Contact request closed; selected appliance model specifications remain needed for millwork.Meghan DuChene2026-09-24partially_resolved
ASK-103INDUCTION VENTILATION: assess downdraft performance and alternatives with client experience; no hood or downdraft model approved.Alyssa Kirk (installation research); Meghan DuChene (design coordination)2026-09-24outstanding
ASK-104WINDOW COORDINATION: Alyssa reports Nada has no concerns extending Michelle’s windows to the floor. That clearance is answered; Michelle has not instructed ordering in the supplied exchange. Confirm final arrangement/drawing choice. Nook: obtain promised Matt/Nada confirmation of 20-inch external projection and adjacent great-room window operation; all-in costs remain ASK-79.Alyssa Kirk / Nada / Matt Dewar2026-09-24partially_resolved
ASK-105STAIR: investigate wood plus matte metal treatment and obtain comparative pricing against the allowance; no metal stair or vendor approved. Alyssa to compare Stairhouse and Neerhof Woodworking against the allowance, with metal feasibility coordinated by Meghan.Meghan DuChene / Alyssa Kirk2026-09-24outstanding
ASK-106TRIM: compare wood jambs without casing, minimal flat casing and drywall returns; show public-room and bedroom applications and their labour costs.Meghan DuChene / Alyssa Kirk2026-09-24outstanding
ASK-107FLOOR HEAT: flag the decision deadline once floor zones are selected; clarify whether the discussed system is electric or hydronic before pricing. Both transcripts use both staple-up and electric wording.Alyssa Kirk2026-09-24outstanding
ASK-108Bedroom 1: retain Meghan wardrobe doors; owner rejected south-wall wood repetition, test non-wood finish. Keep niche/build-out removal and coordinate flush pocket frame; reconcile permit 96-inch door versus portal 84-inch allowance ; interior transom declined by Chris October8. Verify E-100 order drawing: left/right slide, fixed center (Chris); usable fixed band, hardware sweep and clearance for centered 42x24-inch desk and dual monitors. Coordinate safe power, beam positions and finish thickness. Test king/one-bed modes and non-stone bedside tables. Corrected 3D layout now approved by Chris; fabrication details and purchases not approved.Meghan / Alyssa2026-09-25to_send
ASK-109Nada October 7 is coordinating windows, lakeside curtain wall and kitchen steel before an evolved architectural set. Chris October 8 prefers waiting for that set rather than requesting an incomplete progress copy. Our current working design must incorporate sourced post-plan orders/owner changes now under October 11 direction; reconcile to Nada later.Alyssa Kirk / Nada2026-09-25outstanding
ASK-110CLOSED: Alyssa October8 15:40 says Pine Ridge will include Muskoka rafter tails free; Chris16:04: "I love free. Thank you! That's an easy approval". Pricing/owner decision settled. Confirm inclusion in supplier drawings during coordination, not another pricing request.Alyssa / PattyMac2026-10-06closed
ASK-111October15 Muskoka drywall and Soundseals options delivered, October16 MBG revised foundation quote received. Still need second combined quote, perimeter/full-basement like-for-like scope, Roxul contradictions, R60attic/flat-roof and entryR31/ICF/sound clarification, floor alternatives/advisor/electric heat pricing. Do not re-request delivered initial quotes.Alyssa / Nada2026-10-06partially_resolved
ASK-112Coordinate bay seat height, cushion, cranks and visible frame; revised elevations received October 6. Recap keeps nook and large Muskoka window dimensions open; do not treat October 2 general direction as approval of newer dimensions.Alyssa / Meghan2026-10-06outstanding
ASK-113Primary ensuite massing/dimensions delivered October 6. Meghan October 8 supplied Toto Aurora / Washlet S1 sizing example, not purchase approval. Clean plan, plumbing/shower swap and internal-door glass feasibility remain outstanding. Consult current room approvals and product baseline rather than re-requesting delivered examples.Meghan / Alyssa2026-10-06outstanding
ASK-114October13 transcript proposes MondayOctober19 site meeting at11 with PattyMac Michelle and owners, subject to availability. Confirm time/location/attendance, preserve usable stone and scope minimum viable landscaping/path access, drainage and safety; no spending authorized.Alyssa / landscape Michelle2026-10-08partially_resolved
ASK-115Reconcile Mendacity blasting/excavation Oct1-21 with cottage siteworks summary Oct9/100% and foundation Oct21-Nov17. Confirm readiness/crew booking and immediate safe sequential handoff; explain contingency and avoid idle gaps. Date septic blast relative to mobilization, foundation and spring septic install.Alyssa / Bayroc2026-10-12outstanding
ASK-116October16 Kevin via Alyssa recommends removing fractured upper-right rock; other rock can stay. Owner answer requested, not found. Removal after moving earth/building road out of hole. Explicit tree/root and both-rock testing findings/post-work check still not supplied.Alyssa / Bayroc2026-10-12partially_resolved
ASK-117Owner October13 transcript says presence documented, no Englobe report correction needed; do not re-chase interior survey or report amendment. Available own-property records and vibration monitoring remain due.Alyssa / Englobe2026-10-12partially_resolved
ASK-118Decide reviewed image/comparison/design package to share with Meghan; label approvals, proposals and geometry limitations. Do not send until owner decides.Chris / Michelle2026-10-12outstanding
ASK-119CLOSED/superseded: at6:01 October13 transcript Chris says no transom stuff after discussing raised headers and retrofit disruption. Stop carrying October12 future-framing request as current. No new framing spend approved.Alyssa / Meghan / framing contractor2026-10-12closed

Dates on the clock